subject
Business, 06.05.2020 02:05 2Thea12Maine6

According to PMBOK (2012):
Project is a temporary venture made to create a unique product, service or result. ISO 100006 (1997), on the other hand, defines the project as "a unique process, which consists of a group of coordinated and controlled activities with start and end dates, undertaken to achieve an objective, according to specific requirements, including time limitations, cost and resources. "
Analyze the following statements about the projects and their characteristics.
I - The project has its own administration and administrative structure.
II - It must deliver a unique and unprecedented result.
III - The tasks of a project are interdependent.

Which of these is/are correct?

a) I, only.
b) II, only.
c) III, only.
d) I and III, only.
e) I, II, III.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 16:00
Evelyn would like to open a small business that is categorized as a being in the distribution industry. to do this she could open a establishment.
Answers: 1
question
Business, 21.06.2019 16:30
What are some of the miranda restrictions on questioning someone?
Answers: 1
question
Business, 21.06.2019 19:00
Sara is a manager at a restaurant with employees from different cultural backgrounds. which action of sara could employees perceive as an act of favoritism?
Answers: 1
question
Business, 22.06.2019 06:30
Double corporation acquired all of the common stock of simple company for
Answers: 2
You know the right answer?
According to PMBOK (2012):
Project is a temporary venture made to create a unique product, se...
Questions
question
English, 14.12.2021 22:00
question
English, 14.12.2021 22:00
question
Mathematics, 14.12.2021 22:00
question
Social Studies, 14.12.2021 22:00
question
SAT, 14.12.2021 22:00
Questions on the website: 13722363