Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) The project manager cannot force subcontractors to use this project management approach.
B) The feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) Subcontractors routinely operate according to calendar delivery dates.
D) The corporate culture of "no blame" does not naturally extend to subcontractors.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 06:40
As a finance manager at allsports communication, charlie worries about the firm's borrowing requirements for the upcoming year. he knows the benefit of estimating allsports' cash disbursements and short-term investment expectations. facing these concerns, a(n) would provide charlie with valuable information by providing a good estimation of whether the firm will need to do short-term borrowing. capital budget cash budget operating budget line item budget
Answers: 3
question
Business, 22.06.2019 12:10
Profits from using currency options and futures.on july 2, the two-month futures rate of the mexican peso contained a 2 percent discount (unannualized). there was a call option on pesos with an exercise price that was equal to the spot rate. there was also a put option on pesos with an exercise price equal to the spot rate. the premium on each of these options was 3 percent of the spot rate at that time. on september 2, the option expired. go to the oanda.com website (or any site that has foreign exchange rate quotations) and determine the direct quote of the mexican peso. you exercised the option on this date if it was feasible to do so. a. what was your net profit per unit if you had purchased the call option? b. what was your net profit per unit if you had purchased the put option? c. what was your net profit per unit if you had purchased a futures contract on july 2 that had a settlement date of september 2? d. what was your net profit per unit if you sold a futures contract on july 2 that had a settlement date of september 2
Answers: 1
question
Business, 22.06.2019 15:20
Sauer food company has decided to buy a new computer system with an expected life of three years. the cost is $440,000. the company can borrow $440,000 for three years at 14 percent annual interest or for one year at 12 percent annual interest. assume interest is paid in full at the end of each year. a. how much would sauer food company save in interest over the three-year life of the computer system if the one-year loan is utilized and the loan is rolled over (reborrowed) each year at the same 12 percent rate? compare this to the 14 percent three-year loan.
Answers: 3
question
Business, 22.06.2019 16:40
Differentiate between the trait, behavioral, and results-based performance appraisal systems, providing an example where each would be most applicable.
Answers: 1
You know the right answer?
Subcontractor deliveries are difficult to schedule with the critical chain project methodology becau...
Questions
question
Computers and Technology, 07.03.2021 05:30
question
Social Studies, 07.03.2021 05:30
question
Mathematics, 07.03.2021 05:30
question
Biology, 07.03.2021 05:30
question
Mathematics, 07.03.2021 05:30
question
Mathematics, 07.03.2021 05:30
Questions on the website: 13722363