In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:00
How has internet access changed and affected globalization from 2003 to 2013? a ten percent increase in internet access has had little effect on globalization. a twenty percent decrease in internet access has had little effect on globalization. a thirty percent increase in internet access has sped up globalization. a fifty percent decrease in internet access has slowed down globalization.
Answers: 1
question
Business, 22.06.2019 19:30
Nextdoor is an instant messaging application for smartphones. new smartphone users find it easier to connect with friends and relatives through this mobile app when compared to other similar instant messaging applications. hence, it has the largest user base in the industry. thus, nextdoor app's value has increased primarily due to itsa. learning curve effects. b. economies of scale. c. economies of scope. d. network effects.
Answers: 2
question
Business, 22.06.2019 21:30
What term is used to describe the outsourcing of logistics? a. shipper managed inventoryb. hollow logistics(smi)c. sub-logisticsd. e-logisticse. third-party logistics (3pl)
Answers: 1
question
Business, 23.06.2019 01:00
"consists of larger societal forces that affect how a company engages and serves its customers."
Answers: 1
You know the right answer?
In month 9 the following project information is available: actual cost is $2,000, earned value is $2...
Questions
question
Mathematics, 25.09.2020 23:01
Questions on the website: 13722363