Camile owns Crunch Code, a company that provides quick programming solutions. Clients send Crunch projects via their web page and Crunch bangs out the needed code as quickly as possible. Camile has five programmers who do all of the coding. On average, a project arrives once every 4.8 hours, with a standard deviation of 6.00 hours. Each project is assigned to one programmer and that programmer takes on average 19.2 hours to complete each project with a standard deviation of 19.2 hours.

How many uncompleted projects does Crunch Code have in the system on average at any given time? (Include projects waiting for a programmer as well as those being programmed.)
A. 3.45 projects
B. 6.96 projects
C. 12.56 projects
D. 98.72 projects

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 07:10
1. the healthy pantry bought new shelving and financed $7,300 with 36 monthly payments of $267.65 each. suppose the firm pays the loan off with 13 payments left. use the rule of 78 to find the amount of unearned interest. 2. the healthy pantry bought new shelving and financed $7,300 with 36 monthly payments of $267.65 each. suppose the firm pays the loan off with 13 payments left. use the rule of 78 to find the amount necessary to pay off the loan. ! i entered 967.82 for question 1 and 5,455.78 for question 2 and it said it was
Answers: 3
question
Business, 22.06.2019 07:30
When the national economy goes from bad to better, market research shows changes in the sales at various types of restaurants. projected 2011 sales at quick-service restaurants are $164.8 billion, which was 3% better than in 2010. projected 2011 sales at full-service restaurants are $184.2 billion, which was 1.2% better than in 2010. how will the dollar growth in quick-service restaurants sales compared to the dollar growth for full-service places?
Answers: 2
question
Business, 22.06.2019 13:20
Suppose your rich uncle gave you $50,000, which you plan to use for graduate school. you will make the investment now, you expect to earn an annual return of 6%, and you will make 4 equal annual withdrawals, beginning 1 year from today. under these conditions, how large would each withdrawal be so there would be no funds remaining in the account after the 4th withdraw?
Answers: 3
question
Business, 22.06.2019 15:30
The school cafeteria can make pizza for approximately $0.30 a slice. the cost of kitchen use and cafeteria staff runs about $200 per day. the pizza den nearby will deliver whole pizzas for $9.00 each. the cafeteria staff cuts the pizza into eight slices and serves them in the usual cafeteria line. with no cooking duties, the staff can be reduced by half, for a fixed cost of $75 per day. should the school cafeteria make or buy its pizzas?
Answers: 3
You know the right answer?
Camile owns Crunch Code, a company that provides quick programming solutions. Clients send Crunch pr...
Questions
question
Mathematics, 16.01.2021 07:10
question
Mathematics, 16.01.2021 07:10
question
Mathematics, 16.01.2021 07:10
question
History, 16.01.2021 07:10
question
Mathematics, 16.01.2021 07:10
Questions on the website: 13722359