DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month

1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 73% 74% 79% 86%
Total sales (units) 10,550 10,440 10,560 10,560
Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)

1 2 3 4
Move time per unit 0.6 0.5 0.4 0.8
Process time per unit 0.7 0.7 0.7 0.4
Wait time per order before start
of production

9.6 8.0 5.0 4.0
Queue time per unit 3.4 3.1 2.4 1.7
Inspection time per unit 0.6 0.6 0.4 0.6
Required:
1-a. Compute the throughput time for each month. (Round your answers to 1 decimal place.)
Throughput Time
Month 1 days
Month 2 days
Month 3 days
Month 4 days

1-b.
Compute the manufacturing cycle efficiency (MCE) for each month. (Round your percentage answers to 1 decimal place (i. e., 0.1234 should be considered as 12.3%.))

Manufacturing Cycle Efficiency (MCE)
Month 1 %
Month 2 %
Month 3 %
Month 4 %
1-c.
Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.)

Delivery Cycle Time
Month 1 days
Month 2 days
Month 3 days
Month 4 days
3-a.
Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)

Month 5
Throughput time days
Manufacturing cycle efficiency (MCE) %

3-b.
Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)

Month 6
Throughput time days
Manufacturing cycle efficiency (MCE) %

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 09:00
You speak to a business owner that is taking in almost $2000 in revenue each month. the owner still says that they are having trouble keeping the doors open. how can that be possible? use the terms of revenue, expenses and profit/loss in your answer
Answers: 3
question
Business, 22.06.2019 19:00
15. chef a insists that roux is the traditional thickener for bisque. chef b insists that it's rice. which chef is correct? a. neither chef is correct. b. both chefs are correct. c. chef b is correct. d. chef a is correct.
Answers: 1
question
Business, 22.06.2019 23:00
If the reserve requirement is 10 percent, what amount of excess reserves does a bank acquire when a business deposits a $500 check drawn on another bank?
Answers: 2
question
Business, 23.06.2019 01:30
The stock market is -the section of the newspaper where you learn how much a stock is worth -a place where you buy and sell stock -an organized way for people to buy and sell stocks -the same as a brokerage firm
Answers: 1
You know the right answer?
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufa...
Questions
question
Mathematics, 14.05.2021 06:40
Questions on the website: 13722359