A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:30
8. agreement and disagreement among economists suppose that bob, an economist from a university in arizona, and cho, an economist from a public television program, are arguing over saving incentives. the following dialogue shows an excerpt from their debate: cho: i think it's safe to say that, in general, the savings rate of households in today's economy is much lower than it really needs to be to sustain an improvement in living standards. bob: i think a switch from the income tax to a consumption tax would bring growth in living standards. cho: you really think households would change their saving behavior enough in response to this to make a difference? because i don't. the disagreement between these economists is most likely due to . despite their differences, with which proposition are two economists chosen at random most likely to agree? rent ceilings reduce the quantity and quality of available housing. immigrants receive more in government benefits than they contribute in taxes. having a single income tax rate would improve economic performance.
Answers: 1
question
Business, 22.06.2019 17:30
Danielle enjoys working as a certified public accountant (cpa) and assisting small businesses and individuals with managing their finances and taxes. which general area of accounting is her specialty? danielle specialized in
Answers: 1
question
Business, 22.06.2019 17:40
Turrubiates corporation makes a product that uses a material with the following standards standard quantity 8.0 liters per unit standard price $2.50 per liter standard cost $20.00 per unit the company budgeted for production of 3,800 units in april, but actual production was 3,900 units. the company used 32,000 liters of direct material to produce this output. the company purchased 20,100 liters of the direct material at $2.6 per liter. the direct materials purchases variance is computed when the materials are purchased. the materials quantity variance for april is:
Answers: 1
question
Business, 22.06.2019 20:30
Data for hermann corporation are shown below: per unit percent of sales selling price $ 125 100 % variable expenses 80 64 contribution margin $ 45 36 % fixed expenses are $85,000 per month and the company is selling 2,700 units per month. required: 1-a. how much will net operating income increase (decrease) per month if the monthly advertising budget increases by $9,000 and monthly sales increase by $20,000? 1-b. should the advertising budget be increased?
Answers: 1
You know the right answer?
A project to develop technology training seminars is 5 days behind schedule at day 65. It had a plan...