subject
Business, 07.05.2020 15:00 hailiemanuel9362

Using a project start time of 0 (or January 1) and a required project com-pletion time of 180 days (or June 30), calculate the ES, EF, LS, and LF times and TS for each activity. If your calculations result in a project schedule with negative TS, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an accept-able baseline schedule for completing the project within 180 days (or by June 30). Describe the revisions you made answers powerpoint

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 03:00
Tina is applying for the position of a daycare assistant at a local childcare center. which document should tina send with a résumé to her potential employer? a. educational certificate b. work experience certificate c. cover letter d. follow-up letter
Answers: 1
question
Business, 22.06.2019 03:10
Beswick company your team is allocated a project involving a major client, the beswick company. although the organization has many clients, this client, and project, is the largest source of revenue and affects the work of several other teams in the organization. the project requires continuous involvement with the client, so any problems with the client are immediately felt by others in the organization. jamie, a member of your team, is the only person in the company with whom this client is willing to deal. it can be said that jamie has:
Answers: 2
question
Business, 22.06.2019 16:00
What is used by accountant to analyze transactions ?
Answers: 2
question
Business, 23.06.2019 01:50
In january, knox company requisitions raw materials for production as follows: job 1 $915, job 2 $1,590, job 3 $771, and general factory use $704. during january, time tickets show that the factory labor of $6,300 was used as follows: job 1 $2,344, job 2 $1,711, job 3 $1,554, and general factory use $691. prepare the job cost sheets for each of the three jobs.
Answers: 1
You know the right answer?
Using a project start time of 0 (or January 1) and a required project com-pletion time of 180 days (...