In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
WEEK NUMBER
ITEM J 0 1 2 3 4 5
Gross requirements 75 50 70
Projected available balance 40
Net requirements
Planned order receipt
Planned order release
Period 1 2 3 4 5
Gross requirements 76 48 72
Scheduled receipts
Item J Projected available balance
LT = 1 Net requirements
Q = L4L Planned order receipt
Planned order release

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:30
Achecklists should be based on past
Answers: 1
question
Business, 21.06.2019 21:00
Identifying transactions national park tours co. is a travel agency. the nine transactions recorded by national park tours during may 2019, its first month of operations, are indicated in the following t accounts: cash (1) 75,000 (2) 900 (7) 8,150 (3) 1,600 (4) 6,280 (6) 2,700 (9) 2,500 accounts receivable (5) 12,300 (7) 8,150 supplies (2) 900 (8) 660 equipment (3) 8,000 accounts payable (6) 2,700 (3) 6,400 beth worley, capital (1) 75,000 beth worley, drawing (9) 2,500 fees earned (5) 12,300 operating expenses (4) 6,280 (8) 660 indicate for each debit and each credit (a) whether an asset, liability, owner's equity, drawing, revenue, or expense account was affected and (b) whether the account was increased (+) or decreased account debited account credited transaction type effect type effect (1) (2) (3) (4) (5) (6) (7) (8) (9)
Answers: 3
question
Business, 22.06.2019 18:30
Afarmer is an example of what kind of producer?
Answers: 2
question
Business, 22.06.2019 23:50
In june, one of the processinthe assembly department started the month with 25,000 units in its beginning work in process inventory. an additional 310,000 units were transferred in from the prior department during the month to begin processing in the assembly department. there were 30,000 units completed and transferred to the next processing department during the month. how many units the assembly department started the month with 25,000 units in its beginning work in process inventory. an additional 310,000 units were transferred in from the prior department during the month to begin processing in the assembly department. there were 30,000 units completed and transferred to the next processing department during the month. how many units were in its ending work in process inventory
Answers: 2
You know the right answer?
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned or...
Questions
question
Social Studies, 27.08.2020 06:01
question
Mathematics, 27.08.2020 06:01
question
Mathematics, 27.08.2020 06:01
question
Mathematics, 27.08.2020 06:01
question
Mathematics, 27.08.2020 06:01
Questions on the website: 13722361