Red Builders agrees to construct a new building for Blue Co. for a total contract price of $6,000,000. The estimated construction costs at inception was $4,000,000. The construction project was completed after two years. Below are the actual costs for years 1 and 2:

Description Cumulative
Year 1 Year 2
Cost incurred to date 1,200,000 2,500,000
Estimated additional costs to complete 3,600,000 2,100,000
Billings 1,050,000 2,300,000
Cash Collections 1,000,000 1,900,000

Red has determined that this contract qualifies for revenue recognition over time (as opposed to upon completion). As a result, Red Builders should have recognized profit at the end of year 1 in the amount of:

a. $300,000
b. $600,000
c. $1,050,000
d. $1,000,000

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 17:50
Variable rate cd’s = $90 treasury bills = $150 discount loans = $20 treasury notes = $100 fixed rate cds = $160 money market deposit accts. = $140 savings deposits = $90 fed funds borrowing = $40 variable rate mortgage loans $140 demand deposits = $40 primary reserves = $50 fixed rate loans = $210 fed funds lending = $50 equity capital = $120 a. develop a balance sheet from the above data. be sure to divide your balance sheet into rate-sensitive assets and liabilities as we did in class and in the examples. b. perform a standard gap analysis and a duration analysis using the above data if you have a 1.15% decrease in interest rates and an average duration of assets of 5.4 years and an average duration of liabilities of 3.8 years. c. indicate if this bank will remain solvent after the valuation changes. if so, indicate the new level of equity capital after the valuation changes. if not, indicate the amount of the shortage in equity capital.
Answers: 3
question
Business, 22.06.2019 20:30
Discuss ways that oracle could provide client customers with the ability to form better relationships with customers.
Answers: 3
question
Business, 22.06.2019 22:40
Effective capacity is the: a. capacity a firm expects to achieve given the current operating constraints.b. minimum usable capacity of a particular facility.c. sum of all the organization's inputs.d. average output that can be achieved under ideal conditions.e. maximum output of a system in a given period.
Answers: 1
question
Business, 22.06.2019 23:00
Acollege registrar's office requires you to first visit with one of three advisors and then with one of two financial professionals. this system best described as which of the following? a. single server, single phase systemb. multiple server multiphase systemc. multiple server, cross phase systemd. single server, multiphase systeme. multiple server, single phase system
Answers: 2
You know the right answer?
Red Builders agrees to construct a new building for Blue Co. for a total contract price of $6,000,00...
Questions
question
Mathematics, 20.10.2019 16:30
question
History, 20.10.2019 16:30
question
Mathematics, 20.10.2019 16:30
Questions on the website: 13722361