The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August.
Costs:
Actual labor rate $12 per hour
Actual materials price $190 per ton
Standard labor rate $11.50 per hour
Standard materials price $193 per ton
Quantities:
Actual hours incurred and used 4,100 hours
Actual quantity of materials purchased and used 1,500 tons
Standard hours used 4,140 hours
Standard quantity of materials used 1,490 tons
Required:
(a) Compute the total, price, and quantity variances for materials and labor.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 22:20
As a result of a labeling mistake at the chemical factory, a farmer accidentally sprays weedkiller rather than fertilizer on half her land. as a result, she loses half of her productive farmland. if the property of diminishing returns applies to all factors of production, she should expect to seea. a decrease in the marginal productivity of her remaining land and an increase in the marginal productivity of her labor. b. an increase in the marginal productivity of her remaining land and an increase in the marginal productivity of her labor. c. an increase in the marginal productivity of her remaining land and a decrease in the marginal productivity of her labor. d. a decrease in the marginal productivity of her remaining land and a decrease in the marginal productivity of her labor.
Answers: 2
question
Business, 23.06.2019 14:30
List the four stages of ability development. provide an example of a person developing a specific ability. what would each stage look like? career planing
Answers: 1
question
Business, 23.06.2019 16:00
The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. the receipts are enclosed in parentheses. money borrowed to pay building contractor (signed a note) $(276,500 ) (b) payment for construction from note proceeds 276,500 (c) cost of land fill and clearing 11,220 (d) delinquent real estate taxes on property assumed by purchaser 8,340 (e) premium on 6-month insurance policy during construction 12,060 (f) refund of 1-month insurance premium because construction completed early (2,010 ) (g) architectÒ€ℒs fee on building 27,040 (h) cost of real estate purchased as a plant site (land $206,800 and building $55,900) 262,700 (i) commission fee paid to real estate agency 9,620 (j) installation of fences around property 4,030 (k) cost of razing and removing building 10,130 (l) proceeds from salvage of demolished building (4,910 ) (m) interest paid during construction on money borrowed for construction 13,700 (n) cost of parking lots and driveways 17,690 (o) cost of trees and shrubbery planted (permanent in nature) 14,080 (p) excavation costs for new building 2,950 identify each item by letter and list the items in columnar form.
Answers: 1
question
Business, 24.06.2019 00:00
Use the following selected information from wheeler, llc to determine the 2017 and 2016 trend percentages for cost of goods sold using 2016 as the base. 2017 2016 net sales $ 277,700 $ 231,700 cost of goods sold 151,600 129,890 operating expenses 54,940 52,940 net earnings 28,320 20,120
Answers: 3
You know the right answer?
The following direct materials and direct labor data pertain to the operations of Laurel Company for...
Questions
question
Biology, 05.05.2020 23:34
question
Mathematics, 05.05.2020 23:34
question
Mathematics, 05.05.2020 23:34
question
English, 05.05.2020 23:34
Questions on the website: 13722361