Connolly Enterprises manufactures tires for the Formula 1 motor racing circuit. For August 2017 , it budgeted to manufacture and sell 3 comma 100 tires at a variable cost of $ 73 per tire and total fixed costs of $ 53,500 . The budgeted selling price was $116 per tire. Actual results in August 2017 were 3,000 tires manufactured and sold at a selling price of $ 119 per tire. The actual total variable costs were $240,000 , and the actual total fixed costs were $ 50,500. Requirement 1. Prepare a performance report that uses a flexible budget and a static budget. Begin with the actual results, then complete the flexible budget columns and the static budget columns. Label each variance as favorable or unfavorable. (For variances with a $0 balance, make sure to enter "0" in the appropriate field. If the variance is zero, do not select a label.) Actual Results Units sold Revenues Variable costs Contribution margin Fixed costs Operating income Flexible-Budget Flexible Variances Budget Sales-Volume Static Variances Budget
Requirement 2. Comment on the results in requirement 1.
The total static-budget variance in operating income is $ There is a(n) total flexible-budget variance and a(n) sales-volume variance. The sales-volume variance arises solely because actual units manufactured and sold were than the budgeted 3,100 units. The flexible-budget variance in operating income is due primarily to the in unit variable costs. Choose from any list or enter any number in the input fields and then continue to the next question.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 09:20
Which statement best explains the relationship between points a and b? a. consumption reaches its highest point, and then supply begins to fall. b. inflation reaches its highest point, and then the economy begins to expand. c. production reaches its highest point, and then the economy begins to contract. d. unemployment reaches its highest point, and then inflation begins to decrease.
Answers: 2
question
Business, 22.06.2019 16:50
Slow ride corp. is evaluating a project with the following cash flows: year cash flow 0 –$12,000 1 5,800 2 6,500 3 6,200 4 5,100 5 –4,300 the company uses a 11 percent discount rate and an 8 percent reinvestment rate on all of its projects. calculate the mirr of the project using all three methods using these interest rates.
Answers: 2
question
Business, 22.06.2019 17:30
What is the sequence of events that could lead to trade surplus
Answers: 3
question
Business, 22.06.2019 22:40
Utilization will always be lower than efficiency because: a. effective capacity is greater than design capacityb. expected output is less than actual output.c. effective capacity equals design capacity.d. effective capacity is less than design capacity.e. expected output is less than rated capacity.
Answers: 3
You know the right answer?
Connolly Enterprises manufactures tires for the Formula 1 motor racing circuit. For August 2017 , it...
Questions
question
Biology, 13.05.2021 17:40
Questions on the website: 13722361