Given a Project with the following information: Activity Standard Deviation Critical Path Duration
a 2 yes 2
b 1 3
c 1 yes 4
d 3 2
e 1 yes 1
f 2 6
g 2 yes 4
h 1 yes 4
Find:
1. Critical Path
2. Number of Weeks project duration
3. The probability of completing this project in 11 weeks (or less)
4. The probability of completing this project in 14 weeks (or less)
5. The number of weeks required to assure a 96.5% chance of completion
6. If you will receive a bonus of $100,000 if this project is completed within 13 weeks and be fined a penalty of $50,000 if the project takes longer than 17 weeks should you bid the job? Please show quantitative support for your answer.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:30
White company has two departments, cutting and finishing. the company uses a job-order costing system and computes a predetermined overhead rate in each department. the cutting department bases its rate on machine-hours, and the finishing department bases its rate on direct labor-hours. at the beginning of the year, the company made the following estimates: department cutting finishing direct labor-hours 6,000 30,000 machine-hours 48,000 5,000 total fixed manufacturing overhead cost $ 264,000 $ 366,000 variable manufacturing overhead per machine-hour $ 2.00 " variable manufacturing overhead per direct labor-hour " $ 4.00 required: 1. compute the predetermined overhead rate for each department. 2. the job cost sheet for job 203, which was started and completed during the year, showed the following: department cutting finishing direct labor-hours 6 20 machine-hours 80 4 direct materials $ 500 $ 310 direct labor cost $ 108 $ 360 using the predetermined overhead rates that you computed in requirement (1), compute the total manufacturing cost assigned to job 203. 3. would you expect substantially different amounts of overhead cost to be assigned to some jobs if the company used a plantwide predetermined overhead rate based on direct labor-hours, rather than using departmental rates?
Answers: 3
question
Business, 21.06.2019 21:30
Recently, verizon wireless ran a pricing trial in order to estimate the elasticity of demand for its services. the manager selected three states that were representative of its entire service area and increased prices by 5 percent to customers in those areas. one week later, the number of customers enrolled in verizon's cellular plans declined 4 percent in those states, while enrollments in states where prices were not increased remained flat. the manager used this information to estimate the own-price elasticity of demand and, based on her findings, immediately increased prices in all market areas by 5 percent in an attempt to boost the company's 2016 annual revenues. one year later, the manager was perplexed because verizon's 2016 annual revenues were 10 percent lower than those in 2015"the price increase apparently led to a reduction in the company's revenues. did the manager make an error? yes - the one-week measures show demand is inelastic, so a price increase will decrease revenues. yes - the one-week measures show demand is elastic, so a price increase will reduce revenues. yes - cell phone elasticity is likely much larger in the long-run than the short-run. no - the cell phone market must have changed between 2011 and 2012 for this price increase to lower revenues.
Answers: 3
question
Business, 22.06.2019 01:30
The gomez company, a merchandising firm, has budgeted its activity for december according to the following information: β€’ sales at $500,000, all for cash. β€’ merchandise inventory on november 30 was $250,000. β€’ the cash balance at december 1 was $20,000. β€’ selling and administrative expenses are budgeted at $50,000 for december and are paid for in cash. β€’ budgeted depreciation for december is $30,000. β€’ the planned merchandise inventory on december 31 is $260,000. β€’ the cost of goods sold represents 75% of the selling price. β€’ all purchases are paid for in cash. the budgeted cash disbursements for december are:
Answers: 3
question
Business, 22.06.2019 08:30
Which actions can you improve your credit score? (multiple can be selected)having a good credit score should be your prime objective as credit companies analyze your creditworthiness before giving you a loan. there are certain guidelines you can follow to ensure you have a good credit score. always pay your mortgage interest on time. if you are a student, make student loan inquiries before taking any loan. if you have multiple credit cards, manage them judiciously. maintain a healthy balance in your bank account.1. always pay your mortgage interest on time.2. if you are a student, make student loan inquiries before taking any loan.3. if you have multiple credit cards, manage them judiciously.4. maintain a healthy balance in your bank account.
Answers: 1
You know the right answer?
Given a Project with the following information: Activity Standard Deviation Critical Path Duration<...
Questions
question
Social Studies, 06.05.2020 03:06
question
Computers and Technology, 06.05.2020 03:06
Questions on the website: 13722363