Business, 15.07.2020 01:01 jessicap7pg75
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE TIME
PREDECESSOR (WEEKS)
A 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7
a. What is the critical path?
A-B-E-G
A-C-D-E-G
A-C-D-F-G
C-D-F-G
b. How many weeks will it take to complete the project?
Number of weeks
c. How much slack does activity B have?
Slack of activity B weeks
Answers: 1
Business, 21.06.2019 14:30
As he explores his options, sergio notices that some opportunities appear to be riskier than others. when considering various opportunities, sergio should keep in mind that:
Answers: 1
Business, 22.06.2019 13:10
Lin corporation has a single product whose selling price is $136 per unit and whose variable expense is $68 per unit. the company’s monthly fixed expense is $32,400. required: 1. calculate the unit sales needed to attain a target profit of $5,000. (do not round intermediate calculations.) 2. calculate the dollar sales needed to attain a target profit of $8,400.
Answers: 3
Business, 22.06.2019 15:00
Which of the following is least likely to a team solve problems together
Answers: 1
Business, 22.06.2019 23:00
You cannot make copies of media, even as a personal backup, without violating copyright. true
Answers: 3
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE TIME
History, 17.11.2020 23:10
English, 17.11.2020 23:10
Biology, 17.11.2020 23:10
History, 17.11.2020 23:10
Mathematics, 17.11.2020 23:10
Biology, 17.11.2020 23:10
History, 17.11.2020 23:10
Mathematics, 17.11.2020 23:10
History, 17.11.2020 23:10
Physics, 17.11.2020 23:10