An assembly line is to operate eight hours per day with a desired output of 240 units per day. The following table contains information on this product’s task times and precedence relationships. Task Task Time (Seconds) Immediate Predecessor
A 60 ---
B 80 A
C 20 A
D 50 A
E 90 B, C
F 30 C, D
G 30 E, F
H 60 G
a. Draw the precedence diagram. (Answers in Appendix D)
b. What is the workstation cycle time required to produce 240 units per day?
c. Balance this line using the longest task time.
d. What is the efficiency of your line balance, assuming it is running at the cycle time from part (b)?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 08:40
Gerda, a real estate agent, is selling a moderately priced house in a subdivision. she knows from her uncle that the factory being built half a mile from the subdivision will be manufacturing dog food, using a process that creates a very strong odor that permeates the surrounding neighborhood. a buyer, who is unaware of the type of factory under construction, makes an offer on one of the houses gerda is selling, and within a short time, the deal goes through. what does this scenario best illustrate?
Answers: 3
question
Business, 22.06.2019 11:40
In early january, burger mania acquired 100% of the common stock of the crispy taco restaurant chain. the purchase price allocation included the following items: $4 million, patent; $3 million, trademark considered to have an indefinite useful life; and $5 million, goodwill. burger mania's policy is to amortize intangible assets with finite useful lives using the straight-line method, no residual value, and a five-year service life. what is the total amount of amortization expense that would appear in burger mania's income statement for the first year ended december 31 related to these items?
Answers: 2
question
Business, 22.06.2019 19:00
What is an equation of the line in slope intercept formm = 4 and the y-intercept is (0,5)y = 4x-5y = -5x +4y = 4x + 5y = 5x +4
Answers: 1
question
Business, 23.06.2019 11:00
To evaluate solutions, you must usually
Answers: 1
You know the right answer?
An assembly line is to operate eight hours per day with a desired output of 240 units per day. The f...
Questions
question
Physics, 18.03.2021 02:00
question
Mathematics, 18.03.2021 02:00
question
Mathematics, 18.03.2021 02:00
Questions on the website: 13722363