A constraint in the model means:. 1. activity A should be finished within 2 weeks.
2. the total time taken by activity A cannot be more than 2 weeks.
3. activity A cannot be crashed by more than 2 weeks.
4. activity A must be finished in week 2 after the start of the activity.
5. none of the above.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 11:10
Robert black, regional manager for ford in texas and oklahoma, faced a dilemma. the ford f-150 pickup truck was the best-selling pickup ever, yet ford's headquarters in detroit had decided to introduce a completely redesigned f-150. how could mr. black sell both trucks at the same time? he still had "old" f-150s in stock. in his advertising, mr. black referred to the new f-150s as follows: "not a better f-150. just the only truck good enough to be the next f-150." this statement represents ford's of the new f-150.
Answers: 2
question
Business, 23.06.2019 01:30
Bmw receives data transmitted by each new vehicle it sells to employees understand how customers use the products and when service may be needed. this use of technology aids in bmw's efforts to interact in an ongoing basis with its customers.
Answers: 1
question
Business, 23.06.2019 07:00
Select all of the tools you could use to track your expenses. -budget software -spreadsheet -mint© -automatic bill payment -mvelopes®
Answers: 2
question
Business, 23.06.2019 10:00
The american dream includes home ownership. but in the last few years, it's gotten harder and harder to own a home. do you think home ownership is important to most americans today? why or why not?
Answers: 1
You know the right answer?
A constraint in the model means:. 1. activity A should be finished within 2 weeks.
2. the to...
Questions
question
Mathematics, 24.11.2020 17:40
question
Mathematics, 24.11.2020 17:40
question
Mathematics, 24.11.2020 17:40
question
Mathematics, 24.11.2020 17:40
question
English, 24.11.2020 17:40
Questions on the website: 13722363