A proposed nuclear power plant will cost $2.7 billion to build and then will produce cash flows of $350 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $950 million. A. What is project NPV if the discount rate is 3%?
B. What if the discount rate is 16%?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 07:20
Suppose that real interest rates increase across europe. this development will u.s. net capital outflow at all u.s. real interest rates. this causes the loanable funds to because net capital outflow is a component of that curve.
Answers: 1
question
Business, 22.06.2019 11:30
17.     chef a says that garnish should be added to a soup right before serving. chef b says that garnish should be cooked with the other ingredients in a soup. which chef is correct? a. chef a is correct. b. both chefs are correct. c. chef b is correct. d. neither chef is correct. student c   incorrect which is correct answer?
Answers: 2
question
Business, 22.06.2019 14:20
For the year ended december 31, a company has revenues of $323,000 and expenses of $199,000. the company paid $52,400 in dividends during the year. the balance in the retained earnings account before closing is $87,000. which of the following entries would be used to close the dividends account?
Answers: 3
question
Business, 22.06.2019 20:00
If a government accumulates chronic budget deficits over time, what's one possible result? a. a collective action problem b. a debt crisis c. regulatory capture d. an unfunded liability
Answers: 2
You know the right answer?
A proposed nuclear power plant will cost $2.7 billion to build and then will produce cash flows of $...
Questions
question
Mathematics, 19.11.2019 19:31
question
Mathematics, 19.11.2019 19:31
question
Mathematics, 19.11.2019 19:31
Questions on the website: 13722367