Five years ago a dam was constructed to impound irrigation water and to provide flood protection for the area below the dam. Last winter a 100-year flood caused extensive damage both to the dam and to the surrounding area. This was not surprising, since the dam was designed for a 50-year flood. The cost to repair the dam now will be $250,000. Damage in the valley below amount to $750,000. If the spillway is redesigned at a cost of $250,000, the dam may be expected to withstand a 100-year flood without sustaining damage. However, the storage capacity of the dam will not be increased and the probability of damage to the surrounding area will be unchanged. A second dam can be constructed up the river from the existing dam for $1 million. The capacity of the second dam would be more than adequate to provide the desired flood protection. If the second dam is built, redesign of the existing dam spillway will not be necessary, but the $250,000 of repairs must be done. The development in the area below the dam is expected to be complete in 10 years. A new 100-year flood in the meantime would cause a $1 million loss. After 10 years, the loss would be $2 million. In addition, there would be $250,000 of spillway damage if the spillway is not redesigned. A 50-year flood is also lively to cause about $200,000 of damage, but the spillway would be adequate. Similarly, a 25-year flood would case about $50,000 of damage. There are three alternatives:
(1) repair the existing dam for $250,000 but make no other alterations,
(2) repair the existing dam ($250,000) and redesign the spillway to take a 100-year flood ($250,000), and
(3) repair the existing dam ($250,000) and build the second dam ($1 million). Based on an expected annual cash flow analysis, and a 7% interest rate, which alternative should be selected? Draw a decision tree to clearly describe the problem.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 12:30
Diener and wallbom (1976) found that when research participants were instructed to stop working on a problem after a bell sounded, 71 percent continued working when left alone. how many continued to work after the bell if they were made self-aware by working in front of a mirror?
Answers: 2
question
Business, 21.06.2019 20:00
Which of the following statements is true about financial planning
Answers: 2
question
Business, 22.06.2019 18:30
Amanufacturer has paid an engineering firm $200,000 to design a new plant, and it will cost another $2 million to build the plant. in the meantime, however, the manufacturer has learned of a foreign company that offers to build an equivalent plant for $2,100,000. what should the manufacturer do?
Answers: 1
question
Business, 22.06.2019 19:40
Adistinguishing feature of ecological economics is the concept of cost-benefit analysis steady-state economies that, like natural systems, neither grow nor shrink environmental damage and also environmental benefits are external greenwashing to increase public acceptance of products the only healthy economy is one that is growing
Answers: 1
You know the right answer?
Five years ago a dam was constructed to impound irrigation water and to provide flood protection for...
Questions
question
Mathematics, 26.08.2019 10:30
question
Computers and Technology, 26.08.2019 10:30
question
History, 26.08.2019 10:30
Questions on the website: 13722360