The manager of a crew that installs wood floors has tracked the crew's output over the past several weeks. Each worker works 40 hours per week and earns $17 per hour. The wholesale cost of lumber to the company is $5 per square foot and the company charges its customers $15 per square foot of flooring installed. Week Crew Size Lumber Used (sq. ft.) Flooring Installed (sq. ft.)
1 4 480 420
2 3 351 325
3 2 250 238

a. Calculate labor productivity for each of the weeks.
b. Suppose that in addition to labor cost and wholesale lumber cost, the firm's overhead is 120% of its labor cost. Calculate multifactor productivity for each of the weeks shown.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 01:20
As a project manager for a large construction company, shaun decided to make the performance appraisal process as painless as possible for his crew. he spent a considerable amount of time creating performance standards he felt were reasonable, and after six months' time, he scheduled individual appointments with each worker to discuss strengths and weaknesses and areas that needed improvement according to the standards he privately set. some employees were sent to vestibule training, and one even got a promotion with additional compensation. what did he fail to do correctly
Answers: 2
question
Business, 22.06.2019 08:00
How do communism and socialism differ in terms of the role that government plays in the economy ?
Answers: 1
question
Business, 22.06.2019 09:00
Asap describe three different expenses associated with restaurants. choose one of these expenses, and discuss how a manager could handle this expense.
Answers: 1
question
Business, 22.06.2019 12:10
Gwen, a manager at exude apparels inc., received a message from a customer requesting a replacement for a purchased pair of shoes. exude apparels has a clearly stated no-return policy. gwen responded to the customer denying the request in a tactful and clear manner. despite this, the customer submitted a second request. in this scenario, which of the following is an appropriate response to the second request?
Answers: 2
You know the right answer?
The manager of a crew that installs wood floors has tracked the crew's output over the past several...
Questions
question
Mathematics, 02.12.2021 20:00
question
Health, 02.12.2021 20:00
question
Spanish, 02.12.2021 20:00
question
English, 02.12.2021 20:00
Questions on the website: 13722361