Business, 12.08.2020 08:01 savvaggeb

A project manager determined that the project was running behind schedule. If she wants to shorten the total completion, which of the following techniques should be used? A. Crashing
B. Forecasting
C. Gantt chart
D. Resource view
E. Beta distribution

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 22:00
Suppose that with a budget of $110, deborah spends $66 on sushi and $44 on bagels when sushi costs $2 per piece and bagels cost $2 per bagel. but then, the price of bagels falls to $1 per bagel.
Answers: 3
question
Business, 23.06.2019 02:10
Ben is the owner of a small organization with a few employees. he plans to have a data warehouse for the limited number of users in his organization. which data warehouse is most suited for ben's organization? o a. lan-based o b. stationary o c. distributed od. virtual
Answers: 2
question
Business, 23.06.2019 07:50
Suppose for a consumer the marginal utility (mu) of bread is 20 utils and the mu of milk is 10 utils; the price of bread is $3 and the price of milk is $1. given this, a. more utility per dollar is gained from consuming bread than milk. b. more utility per dollar is gained from consuming milk than bread. c. the same amount of utility per dollar is gained from consuming milk as bread. d. the consumer is in consumer equilibrium.
Answers: 1
question
Business, 23.06.2019 14:30
Feedback systems do not always involve negative feedback. economic inflation, which is evidenced by continually rising prices, is a positive feedback system. a positive feedback control system, as shown on the right, adds the feedback signal to the input signal, and the resulting signal is used as the input to the process. a simple model of the price-wage inflationary spiral is shown on the right. add additional feedback loops, such as legislative control or control of the tax rate, to stabilize the system. it is assumed that an increase in workers’ salaries, after some time delay, results an increase in prices. under what conditions could prices be stabilized by falsifying or delaying the availability of cost-ofliving data? how would a national wage and price economic guideline program affect the feedback system?
Answers: 2
You know the right answer?
A project manager determined that the project was running behind schedule. If she wants to shorten t...
Questions
question
Mathematics, 16.04.2020 21:12
Questions on the website: 13722363