If a worker takes 50 hours to perform a task the first time he/she does it, and the learning percentage is 80%
a. How long does it take the worker to do the task the third time it is performed?
b. How long does it take the worker to do all three tasks?
c. How much longer would it take the worker to complete two additional tasks (beyond the first three)?
Answers: 1
Business, 21.06.2019 13:30
For june, gold corp. estimated sales revenue at $600,000. it pays sales commissions that are 4% of sales. the sales manager's salary is $285,000, estimated shipping expenses total 1% of sales, and miscellaneous selling expenses are $15,000. how much are budgeted selling expenses for the month of july if sales are expected to be $540,000.
Answers: 3
Business, 22.06.2019 05:10
The total value of your portfolio is $10,000: $3,000 of it is invested in stock a and the remainder invested in stock b. stock a has a beta of 0.8; stock b has a beta of 1.2. the risk premium on the market portfolio is 8%; the risk-free rate is 2%. additional information on stocks a and b is provided below. return in each state state probability of state stock a stock b excellent 15% 15% 5% normal 50% 9% 7% poor 35% -15% 10% what are each stock’s expected return and the standard deviation? what are the expected return and the standard deviation of your portfolio? what is the beta of your portfolio? using capm, what is the expected return on the portfolio? given your answer above, would you buy, sell, or hold the portfolio?
Answers: 1
Business, 22.06.2019 14:50
Pederson company reported the following: manufacturing costs $480,000 units manufactured 8,000 units sold 7,500 units sold for $90 per unit beginning inventory 2,000 units what is the average manufacturing cost per unit? (round the answer to the nearest dollar.)
Answers: 3
Business, 22.06.2019 17:30
Emery pharmaceutical uses an unstable chemical compound that must be kept in an environment where both temperature and humidity can be controlled. emery uses 825 pounds per month of the chemical, estimates the holding cost to be 50% of the purchase price (because of spoilage), and estimates order costs to be $48 per order. the cost schedules of two suppliers are as follows: vendor 1 vendor 2 quantity price/lb quantity price/lb 1-499 $17 1-399 $17.10 500-999 $16.75 400-799 $16.85 1000+ $16.50 800-1199 $16.60 1200+ $16.25 (a) what is the economic order quantity for each supplier? (b) what quantity should be ordered and which supplier should be used? (c) the total cost for the most economic order sire is $
Answers: 2
If a worker takes 50 hours to perform a task the first time he/she does it, and the learning percent...
Computers and Technology, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Social Studies, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Arts, 02.12.2020 22:00
Biology, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
Spanish, 02.12.2020 22:00
Mathematics, 02.12.2020 22:00
History, 02.12.2020 22:00