MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows: 20X1 20X2
Costs incurred during the year $290,000 $150,000
Estimated additional cost to complete 145,000 —
Billings during the year 260,000 265,000
Cash collections during the year 240,000 285,000

Required:
a. Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.
b. Record the preceding transactions in MSK’s books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 19:20
The following information is from the 2019 records of albert book shop: accounts receivable, december 31, 2019 $ 42 comma 000 (debit) allowance for bad debts, december 31, 2019 prior to adjustment 2 comma 000 (debit) net credit sales for 2019 179 comma 000 accounts written off as uncollectible during 2017 15 comma 000 cash sales during 2019 28 comma 500 bad debts expense is estimated by the method. management estimates that $ 5 comma 300 of accounts receivable will be uncollectible. calculate the amount of bad debts expense for 2019.
Answers: 2
question
Business, 22.06.2019 20:40
Helen tells her nephew, bernard, that she will pay him $100 if he will stop smoking for six months. helen was hopeful that if bernard stopped smoking for six months, he would stop altogether. bernard stops smoking for six months but then resumes his smoking. helen will not pay him. she says that the type of promise she made cannot constitute a binding contract and that, furthermore, it was at least implied that he would stop smoking for good. can bernard legally collect $100 from helen
Answers: 1
question
Business, 22.06.2019 23:00
The sign at the bank reads, "wait here for the first available teller," suggests the use of a waiting line system.a. multiple server, single phaseb. random server, single phasec. single server, multiphased. multiple server, multiphasee. dynamic server, single phase
Answers: 2
question
Business, 22.06.2019 23:10
Amazon inc. does not currently pay a dividend. analysts expect amazon to commence paying annual dividends in three years. the first dividend is expected to be $2 per share. dividends are expected to grow from that point at an annual rate of 4% in perpetuity. investors expect a 12% return from the stock. what should the price of the stock be today?
Answers: 1
You know the right answer?
MSK Construction Company contracted to construct a factory building for $525,000. Construction start...
Questions
question
Physics, 14.07.2019 00:30
question
Physics, 14.07.2019 00:30
question
Mathematics, 14.07.2019 00:30
question
Mathematics, 14.07.2019 00:30
question
Mathematics, 14.07.2019 00:30
Questions on the website: 13722367