When the length of critical path of a project is 40 days and the variance of the project is 4 days, what due date should be set for this project so that the probability of completing the project is 95%? Since it is on days, round the answer to the nearest higher integer. The z value of 95% is 1.645. ?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 17:50
Which of the following is an element of inventory holding costs? a. material handling costs b. investment costs c. housing costs d. pilferage, scrap, and obsolescence e. all of the above are elements of inventory holding costs.
Answers: 1
question
Business, 22.06.2019 19:30
When it is 4: 00 a.m. in halifax, it is 1: 00 p.m. in karachi, and when it is 9: 00 a.m. in karachi, it is 5: 00 a.m. in warsaw. mary left halifax to fly to karachi, but she accidentally left her watch on warsaw time. according to mary’s watch, she left halifax at 9: 40 p.m. on monday. the local time when she arrived at karachi was 3: 00 p.m. tuesday. how long was mary’s flight? a. 9 hours, 20 minutes b. 13 hours, 20 minutes c. 14 hours, 20 minutes d. 17 hours, 20 minutes
Answers: 1
question
Business, 22.06.2019 19:50
On july 7, you purchased 500 shares of wagoneer, inc. stock for $21 a share. on august 1, you sold 200 shares of this stock for $28 a share. you sold an additional 100 shares on august 17 at a price of $25 a share. the company declared a $0.95 per share dividend on august 4 to holders of record as of wednesday, august 15. this dividend is payable on september 1. how much dividend income will you receive on september 1 as a result of your ownership of wagoneer stock
Answers: 1
question
Business, 22.06.2019 21:20
Which of the following best explains why large companies pay less for goods from wholesalers? a. large companies are able to pay for the goods they purchase in cash. b. large companies are able to increase the efficiency of wholesale production. c. large companies can buy all or most of a wholesaler's stock. d. large companies have better-paid employees who are better negotiators.
Answers: 2
You know the right answer?
When the length of critical path of a project is 40 days and the variance of the project is 4 days,...
Questions
Questions on the website: 13722360