A project manager is faced with the following activities and times associated with a building construction for a cancer research facility. Each activity can be crashed at most by 2 weeks. The cost associated with each week time reduction is given below. (note: The 1st crash and 2nd crash costs are associated with the first and second time that a specific activity is crashed. So, if you crash Activity A once, the cost is $9,000, if you have to crash Activity A a second time, the cost is $9,500) Crash Costs
Activity Immediate Predecessor Normal Time (weeks) 1st crash 2nd crash

A 3 $9,000 $9,500
B A 6 $3,500 $6,000
C А 7 $4,000 $5,000
D B 7 $4,500 $6,000
E C 5 $7,000 $7,500
F D, E 8 $10,000 $12,000
G F 2 $14,000 $16,000

What is the minimum cost to crash this project by 2 weeks?

a. $12,000
b. $9,000
c. $16,000
d. $3,500

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:00
Pettijohn inc. the balance sheet and income statement shown below are for pettijohn inc. note that the firm has no amortization charges, it does not lease any assets, none of its debt must be retired during the next 5 years, and the notes payable will be rolled over. balance sheet (millions of $) assets 2016 cash and securities $ 1,554.0 accounts receivable 9,660.0 inventories 13,440.0 total current assets $24,654.0 net plant and equipment 17,346.0 total assets $42,000.0 liabilities and equity accounts payable $ 7,980.0 notes payable 5,880.0 accruals 4,620.0 total current liabilities $18,480.0 long-term bonds 10,920.0 total debt $29,400.0 common stock 3,360.0 retained earnings 9,240.0 total common equity $12,600.0 total liabilities and equity $42,000.0 income statement (millions of $) 2016 net sales $58,800.0 operating costs except depr'n $54,978.0 depreciation $ 1,029.0 earnings bef int and taxes (ebit) $ 2,793.0 less interest 1,050.0 earnings before taxes (ebt) $ 1,743.0 taxes $ 610.1 net income $ 1,133.0 other data: shares outstanding (millions) 175.00 common dividends $ 509.83 int rate on notes payable 1. what is the firm's current ratio? (points : 6) 0.97 1.08 1.20 1.33 2. what is the firm's quick ratio? (points : 6) 0.49 0.61 0.73 0.87 3. what is the firm's total assets turnover? (points : 6) 0.90 1.12 1.40 1.68 4. what is the firm's inventory turnover ratio? (points : 6) 4.38 4.59 4.82 5.06 5. what is the firm's debt ratio? (points : 6) 45.93% 51.03% 56.70% 70.00% 6. what is the firm's roa? (points : 6) 2.70% 2.97% 3.26% 3.59% 7. what is the firm's roe? (points : 6) 8.54% 8.99% 9.44% 9.91%
Answers: 2
question
Business, 22.06.2019 18:10
Consumers who participate in the sharing economy seem willing to interact with total strangers. despite safety and privacy concerns, what do you think is the long-term outlook for this change in the way we think about interacting with people whom we don't know? how can businesses to diminish worries some people may have about these practices?
Answers: 1
question
Business, 22.06.2019 19:50
Aproduction line has three machines a, b, and c, with reliabilities of .96, .86, and .85, respectively. the machines are arranged so that if one breaks down, the others must shut down. engineers are weighing two alternative designs for increasing the line’s reliability. plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. in either case, three machines (a, b, and c) would be used with reliabilities equal to the original three. a. compute overall system reliability under plan 1. (round your intermediate calculations and final answer to 4 decimal places.) reliability b. compute overall system reliability under plan 2. (round your intermediate calculations and final answer to 4 decimal places.) reliability c. which plan will provide the higher reliability? plan2plan1
Answers: 3
question
Business, 23.06.2019 02:50
Camping gear, inc. had 500 units of inventory on hand at the end of the year. these were recorded at a cost of $ 13 each using the lastminusin, firstminusout (lifo) method. the current replacement cost is $ 9 per unit. the selling price charged by camping gear, inc. for each finished product is $ 14. as a result of recording the adjusting entry as per the rule, the gross profit will
Answers: 2
You know the right answer?
A project manager is faced with the following activities and times associated with a building constr...
Questions
question
Mathematics, 09.12.2021 23:50
question
Mathematics, 09.12.2021 23:50
question
Mathematics, 09.12.2021 23:50
question
English, 09.12.2021 23:50
question
Mathematics, 09.12.2021 23:50
Questions on the website: 13722360