Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (not including queue time), are provided below. Over the past 3 months, the old line has averaged 350 parts per day, where one day consists of one 8-hour shift, and has had an average WIP level of 400 parts. The new line has averaged 680 parts per eight-hour day with an average WIP level of 350 parts. Management has been dissatisfied with the performance of the old line because it is achieving lower throughput with higher WIP than the new line, Your job is to evaluate these two lines to the extent possible with the data provided and identify potentially attractive improvement paths for each line by addressing the following questions: Compute rb, To, and Wo for both lines. Which line has larger critical WIP? Explain why.
Compute the best case and worst case performance benchmarks for the old and the new line.
Compare the performance of both lines to their corresponding practical worst case. What can you conclude about the relative performance of the two lines compared to their underlying capabilities? Is management correct in criticizing the old line for inefficiency?
If you were the manager in charge of these lines, what option would you consider first to improve the throughput of the old line? Of the new line?
Old Line
Process Rate per Machine (parts/hr) Number of Machines per station Time (minutes)
Punching 15 4 4.0
Braking 12 4 5.0
Assembly 20 2 3.0
Finishing 50 1 1.2
New Line
Process Rate per Machine (parts/hr) Number of Machines per station Time (minutes)
Punching 120 1 0.50
Braking 120 1 0.50
Assembly 125 1 0.48
Finishing 125 1 0.48

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:10
Ms. sophia jones, the company president, has heard that there are multiple breakeven points for every product. she does not believe this and has asked you to provide the evidence of such a possibility. some information about the company for 2017 is as follows:
Answers: 1
question
Business, 21.06.2019 22:20
Suppose a ceiling fan manufacturer has the total cost function c(x) = 48x + 1485 and the total revenue function r(x) = 75x. (a) what is the equation of the profit function p(x) for this commodity? p(x) = (b) what is the profit on 35 units? p(35) = interpret your result. the total costs are less than the revenue. the total costs are more than the revenue. the total costs are exactly the same as the revenue. (c) how many fans must be sold to avoid losing money? fans
Answers: 1
question
Business, 22.06.2019 04:10
An outside manufacturer has offered to produce 60,000 daks and ship them directly to andretti's customers. if andretti company accepts this offer, the facilities that it uses to produce daks would be idle; however, fixed manufacturing overhead costs would be reduced by 75%. because the outside manufacturer would pay for all shipping costs, the variable selling expenses would be only two-thirds of their present amount. what is andretti's avoidable cost per unit that it should compare to the price quoted by the outside manufacturer?
Answers: 3
question
Business, 22.06.2019 11:00
Which ranks these careers that employers are most likely to hire from the least to the greatest?
Answers: 2
You know the right answer?
Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line de...
Questions
question
Mathematics, 29.05.2020 23:03
question
Mathematics, 29.05.2020 23:04
question
English, 29.05.2020 23:04
Questions on the website: 13722367