A project in its 26th week has an actual cost of $300,000. It was scheduled to have completed $325,000 worth of work at that point in the project. For the work performed to date, the budgeted value is $350,000. The project has a total budget of $500,000. What are the cost and schedule variances for the project

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:50
Consider each of the following cases: case accounting break-even unit price unit variable cost fixed costs depreciation 1 127,400 $ 38 $ 25 $ 711,000 ? 2 124,000 ? 41 2,500,000 $ 900,000 3 5,753 117 ? 171,000 100,000 required: (a) find the depreciation for case 1. (do not round your intermediate calculations.) (b) find the unit price for case 2. (do not round your intermediate calculations.) (c) find the unit variable cost for case 3. (do not round your intermediate calculations.)
Answers: 2
question
Business, 22.06.2019 07:40
Myflvs -question 3 multiple choice worth 2 points)(10.04 hc)in panama city in january, high tide was at midnight. the water level at high tide was 9 feet and1 foot at low tide. assuming the next high tide is exactly 12 hours later and that the height of thewater can be modeled by a cosine curve, find an equation for water level in january for panamacity as a function of time (t).of(t) = 4 + 5of(t) = 5 cost + 4o 460) = 5 cos 1+ 4of(0) = 4 cos + 5
Answers: 1
question
Business, 22.06.2019 11:10
An insurance company estimates the probability of an earthquake in the next year to be 0.0015. the average damage done to a house by an earthquake it estimates to be $90,000. if the company offers earthquake insurance for $150, what is company`s expected value of the policy? hint: think, is it profitable for the insurance company or not? will they gain (positive expected value) or lose (negative expected value)? if the expected value is negative, remember to show "-" sign. no "+" sign needed for the positive expected value
Answers: 2
question
Business, 22.06.2019 18:30
Amanufacturer has paid an engineering firm $200,000 to design a new plant, and it will cost another $2 million to build the plant. in the meantime, however, the manufacturer has learned of a foreign company that offers to build an equivalent plant for $2,100,000. what should the manufacturer do?
Answers: 1
You know the right answer?
A project in its 26th week has an actual cost of $300,000. It was scheduled to have completed $325,0...
Questions
question
History, 31.07.2019 08:30
Questions on the website: 13722363