There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is: A. 3.
B. 5.
C. 9.
D. 16.
E. 25.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
The federal act which provided over $7 billion to the epa to protect and promote "green" jobs and a healthier environment is the - national environmental policy act. - resource recovery act.- resource conservation and recovery act.- american recovery and reinvestment act. - clean air act.
Answers: 1
question
Business, 22.06.2019 05:00
Personal financial planning is the process of creating and achieving financial goals? true or false
Answers: 1
question
Business, 22.06.2019 09:30
Which are the best examples of costs that should be considered when creating a project budget?
Answers: 2
question
Business, 22.06.2019 12:50
Explain whether each of the following events increases or decreases the money supply. a. the fed buys bonds in open-market operations. b. the fed reduces the reserve requirement. c. the fed increases the interest rate it pays on reserves. d. citibank repays a loan it had previously taken from the fed. e. after a rash of pickpocketing, people decide to hold less currency. f. fearful of bank runs, bankers decide to hold more excess reserves. g. the fomc increases its target for the federal funds rate.
Answers: 3
You know the right answer?
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2...
Questions
Questions on the website: 13722362