Business, 11.11.2020 17:50 Bradgarner772

A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week. In order to complete this activity within 10 weeks, you must hire additional general laborers at a cost of $2,000 per week. What is the slope for this activity?A) $0 per week. B) $1,000 per week. C) $2,000 per week. D) $6,000 per week.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 11:00
The role of the credit department includes: a. evaluating customers' credit applications to determine whether they meet the company's approval standards. b. approving all credit applications in order to avoid losing sales. c. collecting cash from customers. d. following unwritten approval standards for processing customers' credit applications.
Answers: 2
question
Business, 22.06.2019 20:30
Before the tools that have come from computational psychiatry are ready to be used in everyday practice by psychiatrics, what is needed
Answers: 1
question
Business, 23.06.2019 03:00
What is the w-4 form used for? filing taxes with the federal government determining the amount of money an employee has paid out in taxes calculating how much tax should be withheld from a person’s paycheck calculating how much income was paid in the previous year
Answers: 1
question
Business, 23.06.2019 12:40
On january 1, a company issued and sold a $398,000, 6%, 10-year bond payable, and received proceeds of $393,000. interest is payable each june 30 and december 31. the company uses the straight-line method to amortize the discount. the journal entry to record the first interest payment is:
Answers: 2
You know the right answer?
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of genera...
Questions
question
Social Studies, 08.03.2021 23:20
question
Mathematics, 08.03.2021 23:20
question
Mathematics, 08.03.2021 23:20
question
Chemistry, 08.03.2021 23:20
Questions on the website: 13722363