Elements of project planning include a. identifying time-cost tradeoffs.
b. determining the project critical path.
c. comparing project schedule objectives.
d. all of these.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 23:10
Kando company incurs a $9 per unit cost for product a, which it currently manufactures and sells for $13.50 per unit. instead of manufacturing and selling this product, the company can purchase product b for $5 per unit and sell it for $12 per unit. if it does so, unit sales would remain unchanged and $5 of the $9 per unit costs assigned to product a would be eliminated. 1. prepare incremental cost analysis. should the company continue to manufacture product a or purchase product b for resale? (round your answers to 2 decimal places.)
Answers: 1
question
Business, 22.06.2019 12:50
Jallouk corporation has two different bonds currently outstanding. bond m has a face value of $50,000 and matures in 20 years. the bond makes no payments for the first six years, then pays $2,100 every six months over the subsequent eight years, and finally pays $2,400 every six months over the last six years. bond n also has a face value of $50,000 and a maturity of 20 years; it makes no coupon payments over the life of the bond. the required return on both these bonds is 10 percent compounded semiannually. what is the current price of bond m and bond n?
Answers: 3
question
Business, 22.06.2019 16:30
Penelope summers received certain income benefits in 2018. she received $1,400 of state unemployment insurance benefits, $2,000 from a federal unemployment trust fund and $3,700 workersโ€™ compensation received for an occupational injury. what amount of the compensation must penelope include in her income
Answers: 1
question
Business, 22.06.2019 20:40
If the ceo of a large, diversified, firm were filling out a fitness report on a division manager (i.e., "grading" the manager), which of the following situations would be likely to cause the manager to receive a better grade? in all cases, assume that other things are held constant.a. the division's basic earning power ratio is above the average of other firms in its industry.b. the division's total assets turnover ratio is below the average for other firms in its industry.c. the division's debt ratio is above the average for other firms in the industry.d. the division's inventory turnover is 6, whereas the average for its competitors is 8.e. the division's dso (days' sales outstanding) is 40, whereas the average for its competitors is 30.
Answers: 1
You know the right answer?
Elements of project planning include a. identifying time-cost tradeoffs.
b. determining the...
Questions
question
History, 21.09.2019 19:10
question
Mathematics, 21.09.2019 19:10
Questions on the website: 13722360