Task C has two immediate predecessors, Tasks A and B. Task C also has two immediate followers, Tasks D and E. Task A has an early finish time of 3 days, and Task B has an early finish time of 5 days. Task D has a late start time of 10 days and Task E has a late start time of 8 days. Task C is 2 days long. What is the early start time of Task C? A. 7 days
B. 5 days
C. 8 days
D. 2 days
E. 6 days

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 07:10
In a team environment, a coordinator is? a person with expert knowledge or skills in a particular area the team needs. a good listener who works to resolve social problems among teammates. a leader who team members focus on their tasks. a good networker who likes to explore new ideas and possiblities.
Answers: 2
question
Business, 22.06.2019 10:40
What would happen to the equilibrium price and quantity of lattés if the cost to produce steamed milk
Answers: 1
question
Business, 22.06.2019 22:50
For 2016, gourmet kitchen products reported $22 million of sales and $19 million of operating costs (including depreciation). the company has $15 million of total invested capital. its after-tax cost of capital is 10%, and its federal-plus-state income tax rate was 36%. what was the firm’s economic value added (eva), that is, how much value did management add to stockholders’ wealth during 2016?
Answers: 1
question
Business, 23.06.2019 01:30
Should i run away or get a boyfriend and be loved again
Answers: 3
You know the right answer?
Task C has two immediate predecessors, Tasks A and B. Task C also has two immediate followers, Tasks...
Questions
question
Health, 14.04.2020 03:47
question
Biology, 14.04.2020 03:47
question
Arts, 14.04.2020 03:47
question
Mathematics, 14.04.2020 03:47
question
Biology, 14.04.2020 03:47
Questions on the website: 13722360