The cost slope of an activity $ 250/day. The normal duration of this activity is 15 days, the crash cost is $1,500 and the maximum crashing possible for the activity is 10 days beyond the normal duration. What is the normal cost of this activity

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 10:30
Marketing1. suppose the average price for a new disposable cell phone is $20, and the total market potential for that product is $4 million. topco, inc. has a planned market share of 10 percent. how many phones does topco have the potential to sell in this market? 20,0002. use the data from question 3 to calculate topco, inc.'s planned market share in dollars. $400,0003. atlantic car rental charges $29.95 per day to rent a mid-size automobile. pacific car rental, atlantic's main competitor, just reduced prices on all its car rentals. in response, atlantic reduced its prices by 5 percent. now how much does it cost to rent a mid-size automobile from atlantic? $28.45
Answers: 1
question
Business, 22.06.2019 22:00
Your sister turned 35 today, and she is planning to save $60,000 per year for retirement, with the first deposit to be made one year from today. she will invest in a mutual fund that's expected to provide a return of 7.5% per year. she plans to retire 30 years from today, when she turns 65, and she expects to live for 25 years after retirement, to age 90. under these assumptions, how much can she spend each year after she retires? her first withdrawal will be made at the end of her first retirement year.
Answers: 3
question
Business, 22.06.2019 22:00
Which of the following statements about nonverbal communication is most accurate? a. the meanings of some gestures can vary among cultures b. the way an e-mail, letter, memo, or report looks can have either a positive or a negative effect on a receiver c. the manner in which we structure and use time can reveal our personalities and attitudes d. all statements are accurate
Answers: 1
question
Business, 23.06.2019 00:30
Anational survey asked people, "how often do you eat out for dinner, instead of at home? " the frequencies were as follows.
Answers: 2
You know the right answer?
The cost slope of an activity $ 250/day. The normal duration of this activity is 15 days, the crash...
Questions
question
History, 10.02.2021 20:10
question
Mathematics, 10.02.2021 20:10
question
Mathematics, 10.02.2021 20:10
Questions on the website: 13722362