Business, 30.12.2020 23:40 usagimiller

We are now part way through a project at a point where we had planned to have 48% of the work done. We have spent $315,191 of the total budget of $811,673. We have completed 53% of the activities. What is the EV

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:10
Suppose that the firm cherryblossom has an orchard they are willing to sell today. the net annual returns to the orchard are expected to be $50,000 per year for the next 20 years. at the end of 20 years, it is expected the land will sell for $30,000. calculate the market value of the orchard if the market rate of return on comparable investments is 16%.
Answers: 1
question
Business, 22.06.2019 13:30
How does hipaa address employee’s access to e-phi?
Answers: 1
question
Business, 22.06.2019 20:40
Which of the following is true concerning the 5/5 lapse rule? a) the 5/5 lapse rule deems that a taxable gift has been made where a power to withdraw in excess of $5,000 or five percent of the trust assets is lapsed by the powerholder. b) the 5/5 lapse rule only comes into play with a single beneficiary trust. c) amounts that lapse under the 5/5 lapse rule qualify for the annual exclusion. d) gifts over the 5/5 lapse rule do not have to be disclosed on a gift tax return.
Answers: 1
question
Business, 22.06.2019 21:10
You are the manager of a large crude-oil refinery. as part of the refining process, a certain heat exchanger (operated at high temperatures and with abrasive material flowing through it) must be replaced every year. the replacement and downtime cost in the first year is $165 comma 000. this cost is expected to increase due to inflation at a rate of 7% per year for six years (i.e. until the eoy 7), at which time this particular heat exchanger will no longer be needed. if the company's cost of capital is 15% per year, how much could you afford to spend for a higher quality heat exchanger so that these annual replacement and downtime costs could be eliminated?
Answers: 1
You know the right answer?
We are now part way through a project at a point where we had planned to have 48% of the work done....
Questions
question
History, 03.10.2019 09:20
Questions on the website: 13722363