Port Aransas Resort Co. (PARC) has decided to move forward with the hotel project on their property at the beach. They have selected a construction company and the project is slated to begin on June 1, 2020. PARC hopes to open the hotel before the summer season begins on May 15, 2021. The builder has given them the following list of activities related to the project and their estimated times (in weeks): ActivityImmediate PredecessorTime
A-9
B-3
C-6
DA, B, C12
EC, D15
FA9
GD, F18
HE12
a. Draw a project network
b. What are the critical activities?
c. What activity has the most slack time and how much slack does this activity have?
d. Will the project be completed by May 15, 2021?
e. If the project had uncertain/variable completion times for some of the activities and the expected completion time is 46 weeks and the variance is 6 weeks, what is the probability that the project will be completed in 48 weeks?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 14:30
Assuming no direct factory overhead costs (i.e., inventory carry costs) and $3 million dollars in combined promotion and sales budget, the deft product manager wishes to achieve a product contribution margin of 35%. given their product currently is priced at $35.00, what would they need to limit the material and labor costs to?
Answers: 3
question
Business, 22.06.2019 10:50
Kimberly has been jonah in preparing his personal income tax forms for a couple of years. jonah's boss recommended kimberly because she had done a good job setting up the company's new accounting system. jonah is very satisfied with kimberly's work and feels that the fees she charges are quite reasonable. kimberly would be classified as a(n) (a) independent auditor (b) private accountant (c) public accountant (d) accounting broker
Answers: 1
question
Business, 22.06.2019 17:40
Croy inc. has the following projected sales for the next five months: month sales in units april 3,850 may 3,875 june 4,260 july 4,135 august 3,590 croy’s finished goods inventory policy is to have 60 percent of the next month’s sales on hand at the end of each month. direct material costs $2.50 per pound, and each unit requires 2 pounds. raw materials inventory policy is to have 50 percent of the next month’s production needs on hand at the end of each month. raw materials on hand at march 31 totaled 3,741 pounds. 1. determine budgeted production for april, may, and june. 2. determine the budgeted cost of materials purchased for april, may, and june. (round your answers to 2 decimal places.)
Answers: 3
question
Business, 22.06.2019 23:30
Which external factor has enabled addition of special effects in advertisements and tracking of responses of customers over websites?
Answers: 3
You know the right answer?
Port Aransas Resort Co. (PARC) has decided to move forward with the hotel project on their property...
Questions
question
Mathematics, 21.10.2020 01:01
question
Mathematics, 21.10.2020 01:01
Questions on the website: 13722367