Ely Company has two support departments, Maintenance Department and Personnel Department, and two producing departments, X and Y. The Maintenance Department costs of $60,000 are allocated on the basis of standard service hours used. The Personnel Department costs of $9,000 are allocated on the basis of number of employees. The direct costs of Departments X and Y are $18,000 and $30,000, respectively. Data on standard service hours and number of employees are as follows: Data on standard service hours and number of employees are as follows:
Maint. Person. Dept. Dept.
Dept. Dept. X Y
Standard service hours used 100 50 300 150
Number of employees 5 10 45 45
Direct labor hours 50 50 250 250

Predetermined overhead rates for Departments X and Y, respectively, are based on direct labor hours.

What is the overhead rate for Department Y assuming the direct method is used?

a. $120.00
b. $218.00
c. $109.00
d. $250.00

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 02:10
Materials purchases (on credit). direct materials used in production. direct labor paid and assigned to work in process inventory. indirect labor paid and assigned to factory overhead. overhead costs applied to work in process inventory. actual overhead costs incurred, including indirect materials. (factory rent and utilities are paid in cash.) transfer of jobs 306 and 307 to finished goods inventory. cost of goods sold for job 306. revenue from the sale of job 306. assignment of any underapplied or overapplied overhead to the cost of goods sold account. (the amount is not material.) 2. prepare journal entries for the month of april to record the above transactions.
Answers: 1
question
Business, 22.06.2019 12:50
You are working on a bid to build two city parks a year for the next three years. this project requires the purchase of $249,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the three-year project life. ignore bonus depreciation. the equipment can be sold at the end of the project for $115,000. you will also need $18.000 in net working capital for the duration of the project. the fixed costs will be $37000 a year and the variable costs will be $148,000 per park. your required rate of return is 14 percent and your tax rate is 21 percent. what is the minimal amount you should bid per park? (round your answer to the nearest $100) (a) $214,300 (b) $214,100 (c) $212,500 (d) $208,200 (e) $208,400
Answers: 3
question
Business, 22.06.2019 19:20
Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipment six years ago was 187 and is now 194. the cost-capacity factor is 0.6. the plant engineering staff is considering a 120-kw unit of the same general design to power a small isolated plant. assume we want to add a precompressor, which (when isolated and estimated separately) currently costs $13291. determine the total cost of the 120-kw unit. (hint: skip $ and comma symbols)
Answers: 3
You know the right answer?
Ely Company has two support departments, Maintenance Department and Personnel Department, and two pr...
Questions
question
History, 17.04.2021 01:00
Questions on the website: 13722362