In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 2022 2023
Cost incurred during the year $2,184,000 $3,510,000 $2,316,600
Estimated costs to complete as of year-end 5,616,000 2,106,000 0
Billings during the year 2,120,000 3,574,000 4,306,000
Cash collections during the year 1,860,000 3,400,000 4,740,000
Westgate recognizes revenue over time according to percentage of completion.
Required:
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
Answers: 2
Business, 22.06.2019 00:10
Which of the following is a problem for the production of public goods?
Answers: 2
Business, 22.06.2019 02:30
Based on the supply and demand theory, why do medical doctors earn higher wages than child-care workers?
Answers: 1
Business, 22.06.2019 16:20
The assumptions of the production order quantity model are met in a situation where annual demand is 3650 units, setup cost is $50, holding cost is $12 per unit per year, the daily demand rate is 10 and the daily production rate is 100. the production order quantity for this problem is approximately:
Answers: 1
Business, 22.06.2019 17:30
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Cla...
History, 19.03.2020 02:39
Business, 19.03.2020 02:39
Computers and Technology, 19.03.2020 02:39
Mathematics, 19.03.2020 02:39
Mathematics, 19.03.2020 02:39