A contractor is planning to pour concrete on Monday morning, but he has heard a weather forecast that rain is expected. The probabilities of rain are 0.8 on Monday, 0.6 on Tuesday, 0.3 on Wednesday, and 0.1 on Thursday and each succeeding day for five days. If it rains on the day that concrete is poured, there will be an immediate 50,000 damage cost and a delay of five days in the construction schedule. For every day of delay, 20,000 is lost. The delay cost applies even if it is the contractor who decides to delay the pour. Required:
a. Determine on which day the concrete should be poured.
b. What is the associated expected cost?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 06:00
Use this image to answer the following question. when the economy is operating at point b, the us congress is most likely to follow
Answers: 3
question
Business, 22.06.2019 08:40
Mcdonald's fast-food restaurants have a well-designed training program for all new employees. each new employee is supposed to learn how to perform standardized tasks required to maintain mcdonald's service quality. due to labor shortages in some areas, new employees begin work as soon as they are hired and do not receive any off-the-job training. this nonconformity to standards creates
Answers: 2
question
Business, 22.06.2019 10:30
You meet that special person and get married. amazingly your spouse has exactly the same income you do 47,810. if your tax status is now married filing jointly what is your tax liability
Answers: 2
question
Business, 22.06.2019 18:00
What would not cause duff beer’s production possibilities curve to expand in the short run? a. improved manufacturing technology b. additional resources c. increased demand
Answers: 1
You know the right answer?
A contractor is planning to pour concrete on Monday morning, but he has heard a weather forecast tha...
Questions
question
Social Studies, 01.10.2021 19:50
Questions on the website: 13722361