Business, 07.04.2021 01:00 ortegaly000

Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities is A- 3.5 months

B- 5.7 months

C - 1.6 months

D- 2.1 months

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:00
The maximum tax rate on estates and gifts
Answers: 1
question
Business, 21.06.2019 20:30
If delta airlines were to significantly change its fare structure and flight schedule to enhance its competitive position in response to aggressive price cutting by southwest airlines, this would be an example ofanswers: explicit collusion.tacit collusion.competitive dynamics.a harvest strategy.
Answers: 3
question
Business, 21.06.2019 22:30
For many years, kellogg's frosted flakes, a ready-to-eat breakfast cereal, was perceived as a cereal for children. tony the tiger, a cartoon character, extolled frosted flakes, and advertisements depicted children enjoying the product with tony in competitive situations. recently, in response to declining sales of frosted flakes, the cereal maker has adopted a new series of advertisements that show adults admitting that they enjoy frosted flakes, too. kellogg's is attempting to
Answers: 1
question
Business, 21.06.2019 23:30
Renaldo scanlon is a financial consultant. he earns $30 per hour and works 32.5 hours a week. what is his straight-time pay?
Answers: 1
You know the right answer?
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the...
Questions
question
Mathematics, 11.02.2021 21:00
question
Mathematics, 11.02.2021 21:00
question
Social Studies, 11.02.2021 21:00
question
English, 11.02.2021 21:00
question
Mathematics, 11.02.2021 21:00
question
Mathematics, 11.02.2021 21:00
question
Mathematics, 11.02.2021 21:00
Questions on the website: 13722367