Two roadway design are under consideration. Design 1A will cost $3 million to build and $100,000 per year to maintain. Design 1B will cost $3.5 million to build and $40,000 per year to maintain. Both designs are assumed to be permanent. Use an AW based rate of return equation to determine (a) the breakeven ROR, and (b) which design is preferred at a MARR of 10% per year

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 04:10
What is the difference between secure bonds and naked bonds?
Answers: 1
question
Business, 22.06.2019 14:30
Stella company sells only two products, product a and product b. product a product b total selling price $50 $30 variable cost per unit $20 $10 total fixed costs $2,110,000 stella sells two units of product a for each unit it sells of product b. stella faces a tax rate of 40%. stella desires a net afterminustax income of $54,000. the breakeven point in units would be
Answers: 3
question
Business, 22.06.2019 19:30
Which of the following constitute the types of unemployment occurring at the natural rate of unemployment? a. frictional and cyclical unemployment.b. structural and frictional unemployment.c. cyclical and structural unemployment.d. frictional, structural, and cyclical unemployment.
Answers: 2
question
Business, 22.06.2019 20:00
What is the difference between total utility and marginal utility? a. marginal utility is subject to the law of diminishing marginal utility while total utility is not. b. total utility represents the consumer optimum while marginal utility gives the total utility per dollar spent on the last unit. c. total utility is the total amount of satisfaction derived from consuming a certain amount of a good while marginal utility is the additional satisfaction gained from consuming an additional unit of the good. d. marginal utility represents the consumer optimum while total utility gives the total utility per dollar spent on the last unit.
Answers: 3
You know the right answer?
Two roadway design are under consideration. Design 1A will cost $3 million to build and $100,000 per...
Questions
Questions on the website: 13722359