The following labor standards have been established for a particular product: Standard labor-hours per unit of output 8.4 hours
Standard labor rate $12.20 per hour

The following data pertain to operations concerning the product for the last month:

Actual hours worked 6,200 hours
Actual total labor cost $73,160
Actual output 950 units

Required:
What is the labor efficiency variance for the month?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 08:30
Match the given situations to the type of risks that a business may face while taking credit. 1. beta ltd. had taken a loan from a bank for a period of 15 years, but its sales are gradually showing a decline. 2. alpha ltd. has taken a loan for increasing its production and sales, but it has not conducted any research before making this decision. 3. delphi ltd. has an overseas client. the economy of the client’s country is going through severe recession. 4. delphi ltd. has taken a short-term loan from the bank, but its supply chain logistics are not in place. a. foreign exchange risk b. operational risk c. term of loan risk d. revenue projections risk
Answers: 3
question
Business, 22.06.2019 08:30
Acompany recorded a check in its accounting records as $87. however, the check was actually written for $78 and it cleared the bank as $78. what adjustment is needed to the personal statement? a. decrease by $9 b. increase by $9 c. decrease by $18 d. increase by $9
Answers: 2
question
Business, 22.06.2019 18:30
Jason started last week with $900 in his checking account. during the week, he wrote the checks below. at the end of the week, jason received a paycheck for $534.59. he recorded all of these transactions in his check register. trans typ./ check no. date description of transaction payment/ debit deposit/ credit (+) balance 900 00 241 12/4 miller's food market 53.21 53 21 groceries 846 79 242 12/7 frank's auto parts 24.05 24 05 oil and filter 822 74 243 12/8 mike's barber shop 15.00 15 00 haircut 807 74 deposit 12/9 paycheck 534.59 534 59 1,342 33 evaluate jason's check register. a. jason did a good job; everything is correct. b. the final balance is wrong; jason did not add everything correctly. c. jason should have written debit instead of deposit for the transaction type. d. jason entered the amount for his paycheck in the wrong column.
Answers: 3
question
Business, 22.06.2019 20:00
Modern firms increasingly rely on other firms to supply goods and services instead of doing these tasks themselves. this increased level of is leading to increased emphasis on management.
Answers: 2
You know the right answer?
The following labor standards have been established for a particular product: Standard labor-hours...
Questions
question
Biology, 28.08.2020 18:01
question
Biology, 28.08.2020 18:01
question
Mathematics, 28.08.2020 18:01
question
Mathematics, 28.08.2020 18:01
Questions on the website: 13722362