What are the consequences to the schedule if completion of a primary task is delayed?

a. the beginnings of all related dependent tasks are also delayed.
b. time to complete the dependent task will have to be shortened.
c. the entire project schedule will be delayed.
d. the chief finance officer of the divisional office.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 08:30
Hi inr 2002 class! i just uploaded a detailed study guide for this class. you can check-out a free preview by following the link below feel free to reach-out to me if you need a study buddy or have any questions. goodluck!
Answers: 1
question
Business, 22.06.2019 09:30
An object that is clicked on and takes the presentation to a new targeted file is done through a
Answers: 2
question
Business, 22.06.2019 17:30
One of your new suppliers, kim, has been hearing rumors about your firm’s lack of capability to deliver high quality products and writes an email asking you to address the claims being made. in replying to her, you want to be sure that you are very clear and leave no room for misinterpretation. which of the following aspects of effective communication should you give the most attention? (a) making sure you understand kim’s areas of expertise. (b) supporting your reply with relevant data and facts. (c) establishing your credibility as an expert. (d) paying attention to implied communications.
Answers: 2
question
Business, 22.06.2019 21:10
Skychefs, inc. prepares in-flight meals for a number of major airlines. one of the company's products is grilled salmon in dill sauce with baby new potatoes and spring vegetables. during the most recent week, the company prepared 4000 of these meals using 960 direct labor hours. the company paid these direct labor workers a total of $19,200 for this work, or $20.00 per hour. according to standard cost card for this meal, it should require 0.25 direct labour-hours at a cost of $19.75 per hour.1. what is the standard labor-hours allowed (sh) to prepare 4,000 meals? 2. what is the standard labor cost allowed (sh x sr) to prepare 4,000 meals? 3. what is the labor spending variance? 4. what is the labor rate variance and the labor efficiency variance?
Answers: 3
You know the right answer?
What are the consequences to the schedule if completion of a primary task is delayed?

a...
Questions
question
Mathematics, 17.03.2020 20:31
Questions on the website: 13722363