During 2019, Sheridan Company expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Sheridan applied overhead based on direct labor cost. Actual production required an overhead cost of $340000, $590000 in materials used, and $230000 in labor. All of the goods were completed. What amount was transferred to Finished Goods

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 09:00
Afood worker has just rinsed a dish after cleaning it.what should he do next?
Answers: 2
question
Business, 22.06.2019 11:20
Mae jong corp. issues $1,000,000 of 10% bonds payable which may be converted into 10,000 shares of $2 par value ordinary shares. the market rate of interest on similar bonds is 12%. interest is payable annually on december 31, and the bonds were issued for total proceeds of $1,000,000. in accounting for these bonds, mae jong corp. will: (a) first assign a value to the equity component, then determine the liability component. (b) assign no value to the equity component since the conversion privilege is not separable from the bond.(c) first assign a value to the liability component based on the face amount of the bond.(d) use the “with-and-without” method to value the compound instrument.
Answers: 3
question
Business, 22.06.2019 13:00
Apopular low-cost airline, parson corp., has gone out of business. although the service and price provided by the airline was what customers wanted, the larger airlines were able to drive the low-cost airline out of business through an aggressive price war. which component of the competitive environment does this illustrate? a) threat of new entrants b)competitors c) economic factors d) customers d) regulators
Answers: 1
question
Business, 22.06.2019 18:50
)a business incurs the following costs per unit: labor $125/unit, materials $45/unit, and rent $250,000/month. if the firm produces 1,000,000 units a month, calculate the following: a. total variable costs b. total fixed costs c. total costs
Answers: 1
You know the right answer?
During 2019, Sheridan Company expected Job No. 26 to cost $300000 of overhead, $500000 of materials,...
Questions
question
Social Studies, 12.03.2020 00:36
question
English, 12.03.2020 00:36
Questions on the website: 13722367