DL variances Logen Construction builds standard prefabricated wooden frames for walls. Each frame requires five direct labor hours and the standard hourly direct labor rate is $18. During July, the company produced 670 frames and worked 3,310 direct labor hours. Payroll records indicate that workers earned $60,407.50.
a. What were the standard hours for July production?
hours
b. What was the actual hourly wage rate? Round your answer to the nearest cent.
$ per hour
c. Calculate the direct labor variances. Round your answers to the nearest cent.
Labor Rate Variance$
Labor Efficiency Variance$
Total Labor Variance$

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 09:50
Why should managers invest any excess cash
Answers: 1
question
Business, 22.06.2019 19:40
Which term describes an alternative to car buying where monthly payments are paid for a specific period of time, after which the vehicle is returned to the dealership or bought? a. car financing b. car maintenance c. car leasing d. car ownership
Answers: 3
question
Business, 22.06.2019 23:00
Doogan corporation makes a product with the following standard costs: standard quantity or hours standard price or rate direct materials 2.0 grams $ 7.00 per gram direct labor 1.6 hours $ 12.00 per hour variable overhead 1.6 hours $ 6.00 per hour the company produced 5,000 units in january using 10,340 grams of direct material and 2,320 direct labor-hours. during the month, the company purchased 10,910 grams of the direct material at $7.30 per gram. the actual direct labor rate was $12.85 per hour and the actual variable overhead rate was $5.80 per hour. the company applies variable overhead on the basis of direct labor-hours. the direct materials purchases variance is computed when the materials are purchased. the materials quantity variance for january is:
Answers: 1
question
Business, 22.06.2019 23:10
Tony prince is the project manager for the recreation and wellness intranet project. team members include you, a programmer/analyst and aspiring project manager; patrick, a network specialist; nancy, a business analyst; and bonnie, another programmer/analyst. other people are supporting the project from other departments, including yusaff from human resources and cassandra from finance. assume that these are the only people who can be assigned and charged to work on project activities. recall that your schedule and cost goals are to complete the project in six months for under $200,000.task 2identify at least eight milestones for the recreation and wellness intranet project. write a short paper describing each milestone using the smart criteria. discuss how determining these milestones might add activities or tasks to the gantt chart. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone.
Answers: 3
You know the right answer?
DL variances Logen Construction builds standard prefabricated wooden frames for walls. Each frame r...
Questions
question
Mathematics, 19.11.2020 17:40
question
Mathematics, 19.11.2020 17:40
question
Mathematics, 19.11.2020 17:40
question
History, 19.11.2020 17:40
question
Mathematics, 19.11.2020 17:40
Questions on the website: 13722360