The demand for subassembly S is 90 units in week 7. Each unit of S requires 2 unit of T and 2 units of U. Each unit of T requires 2 unit of V, 1 units of W, and 1 unit of X. Finally, each unit of U requires 1 units of Y and 3 units of Z. ONe firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 weeks to make V, 3 weeks to make W, 2 week to make X, 2 weeks to make Y, and 2 week to make Z. In addition to 90 units of S, there is also demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirement plan to reflect this change.
a) Using the infomation construct a gross material requirements plan.
b) Construct a net material requirements plan of the on-hand inventory.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:50
What is the best definition of a conclusion?
Answers: 1
question
Business, 22.06.2019 11:30
Which of the following is not an example of one of the four mail advantages of prices on a free market economy
Answers: 1
question
Business, 22.06.2019 15:00
Beagle autos is known for its affordable and reliable brand of consumer vehicles. because its shareholders expect to see an improved rate of growth in the coming years, beagle's executives have decided to diversify the company's range of products so that at least 40 percent of the firm's revenue is generated by new business units. however, the company's resources, capabilities, and competencies are limited to producing other forms of motorized vehicles, such as motorcycles and all-terrain vehicles (atvs). which type of corporate diversification strategy should beagle pursue?
Answers: 1
question
Business, 22.06.2019 16:30
Summarize the specific methods used by interest groups in order to influence governmental decisions making in all three branches of government. provide at least two examples from each branch.
Answers: 3
You know the right answer?
The demand for subassembly S is 90 units in week 7. Each unit of S requires 2 unit of T and 2 units...
Questions
question
Mathematics, 15.04.2021 09:10
question
Biology, 15.04.2021 09:10
question
Geography, 15.04.2021 09:10
question
Biology, 15.04.2021 09:10
Questions on the website: 13722363