A - 4 0 4 6 10 B - 5 0 5 0 5 C A 3 4 7 10 13 D B 8 5 13 5 13 E B 2 5 7 16 18 F C, D 3 13 16 15 18 G C, D 7 13 20 13 20 H E, F 2 16 18 18 20 How long can activity C be delayed without delaying the completion of the project

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 09:30
Which of these is not a result of regular exercise
Answers: 1
question
Business, 22.06.2019 16:40
Shawn received an e-mail offering a great deal on music, movie, and game downloads. he has never heard of the company, and the e-mail address and company name do not match. what should shawn do?
Answers: 2
question
Business, 22.06.2019 16:50
The cost of labor is significantly lower in many countries than in the united states. if you move manufacturing to a facility to a country labeled as part of the axis of evil and a threat to world peace you will increase the net income of your client by $10 million per the facility is located in a country which limits personal freedom and engages in state sponsored terrorism. imagine you are a marketing consultant. (a) what would you tell the executives to do? (b) what are the alternatives? what are your recommendations? why do you recommend this course of action?
Answers: 1
question
Business, 22.06.2019 21:10
Acompany has two products: standard and deluxe. the company expects to produce 36,375 standard units and 62,240 deluxe units. it uses activity-based costing and has prepared the following analysis showing budgeted cost and cost driver activity for each of its three activity cost pools.budgeted activity of cost driver activity cost pool budgeted cost standard deluxe activity 1 $ 93,000 2,500 5,250 activity 2 $ 92,000 4,500 5,500 activity 3 $ 87,000 3,000 2,800 what is the overhead cost per unit for the standard units? what is the overhead cost per unit for the deluxe units? (round activity rate and cost per unit answers to 2 decimal places.)activity expected costs expected activity driver activity rate1 93,000 2 92,000 3 87,000 standard activity activity driver activity rate allocated costs1 2 3
Answers: 2
You know the right answer?
A - 4 0 4 6 10 B - 5 0 5 0 5 C A 3 4 7 10 13 D B 8 5 13 5 13 E B 2 5 7 16 18 F C, D 3 13 16 15 18 G...
Questions
question
Computers and Technology, 03.12.2021 05:10
Questions on the website: 13722367