Jones Electric Motors uses a Kanban system to make motors for several garage door companies in the southeastern United States. The daily demand for motor housings used
in manufacturing is 200 units. The average waiting time for a container of parts is 0.2
day. The processing time for a container of housings is 0.1 day, and a container holds
10 housings.
a. Jones expects to maintain 8 containers and to do so how much safety stock
should be maintained?
b. Use the safety stock from part (a) to determine the required reduction in waiting
time if one container was removed. Assume that all other parameters remain
constant.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:20
Homestead jeans co. has an annual plant capacity of 65,000 units, and current production is 45,000 units. monthly fixed costs are $54,000, and variable costs are $29 per unit. the present selling price is $42 per unit. on november 12 of the current year, the company received an offer from dawkins company for 18,000 units of the product at $32 each. dawkins company will market the units in a foreign country under its own brand name. the additional business is not expected to affect the domestic selling price or quantity of sales of homestead jeans co. a. prepare a differential analysis dated november 12 on whether to reject (alternative 1) or accept (alternative 2) the dawkins order. if an amount is zero, enter zero "0". for those boxes in which you must enter subtracted or negative numbers use a minus sign.
Answers: 1
question
Business, 21.06.2019 20:30
Anewspaper boy is trying to perfect his business in order to maximize the money he can save for a new car. daily paper sales are normally distributed, with a mean of 100 and standard deviation of 10. he sells papers for $0.50 and pays $0.30 for them. unsold papers are trashed with no salvage value. how many papers should he order each day and what % of the time will he experience a stockout? are there any drawbacks to the order size proposed and how could the boy address such issues?
Answers: 3
question
Business, 22.06.2019 00:30
Needs to schedule the staffing of the center. it is open from 8am until midnight. larry has monitored the usage of the center at various times of the day and determined that the following number of computer consultants are required: time of dayminimum number of consultants required to be on duty8 am-noon4noon-4 pm84pm-8pm108pm-midnight6 two types of computer consultants can be hired: full-time and part-time. the full- time consultants work for eight consecutive hours in any of the shifts: morning (8am- 4pm), afternoon (noon-8pm) and evening (4pm-midnight). full-time consultants are paid $14 per hour. part-time consultants can be hired to work any of the four shifts listed in the table. part-time consultants are paid $12 per hour. an additional requirement is that during every time period, there must be at least two full-time consultants on duty for every part-time consultant on duty. larry would like to determine how many full-time and part-time consultants should work each shift to meet the above requirements at the minimum possible cost. formulate this as an lp problem. you must define your variables clearly
Answers: 2
question
Business, 22.06.2019 14:10
Carey company is borrowing $225,000 for one year at 9.5 percent from second intrastate bank. the bank requires a 15 percent compensating balance. the principal refers to funds the firm can effectively utilize (amount borrowed โˆ’ compensating balance). a. what is the effective rate of interest? (use a 360-day year. input your answer as a percent rounded to 2 decimal places.) b. what would the effective rate be if carey were required to make 12 equal monthly payments to retire the loan?
Answers: 1
You know the right answer?
Jones Electric Motors uses a Kanban system to make motors for several garage door companies in the...
Questions
question
English, 13.01.2021 20:10
question
Spanish, 13.01.2021 20:10
question
Mathematics, 13.01.2021 20:10
question
Arts, 13.01.2021 20:10
question
Mathematics, 13.01.2021 20:10
question
Advanced Placement (AP), 13.01.2021 20:10
question
English, 13.01.2021 20:10
Questions on the website: 13722367