Bill Fredlund, president of Lincoln Log Construction, is considering placing a bid on a building project. Bill has determined that five tasks would need to be performed to carry out the proj- ect. Using the PERT three-estimate approach, Bill has obtained the estimates in the next table for how long these tasks will take. Also shown are the precedence relationships for these tasks. There is a penalty of $500,000 if the project is not completed in 11 weeks. Therefore, Bill is very interested in how likely it is that his company could finish the project in time.

(a) Construct the project network for this project. T

(b) Find the estimate of the mean and variance of the duration

of each activity.

(c) Find the mean critical path. T

(d) Find the approximate probability of completing the project

within 11 weeks.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 02:30
The dollar value generated over decades of customer loyalty to your company is known as brand equity. viability. sustainability. luck.
Answers: 1
question
Business, 22.06.2019 15:30
Brenda wants a new car that will be dependable transportation and look good. she wants to satisfy both functional and psychological needs. true or false
Answers: 1
question
Business, 22.06.2019 19:00
1. what must one do to perform the essential managerial task of controlling in achieving organizational goals? a. motivate, coordinate, and energize individuals and groups to work together to achieve organizational goals b. choose appropriate organizational goals and courses of action to best achieve those goals c. establish task and authority relationships that allow people to work together to achieve organizational goals d. establish accurate measuring and monitoring systems to evaluate how well the organization has achieved its goals
Answers: 1
question
Business, 22.06.2019 20:30
When patey pontoons issued 4% bonds on january 1, 2018, with a face amount of $660,000, the market yield for bonds of similar risk and maturity was 5%. the bonds mature december 31, 2021 (4 years). interest is paid semiannually on june 30 and december 31?
Answers: 1
You know the right answer?
Bill Fredlund, president of Lincoln Log Construction, is considering placing a bid on a building pro...
Questions
question
Mathematics, 14.04.2021 22:40
question
Business, 14.04.2021 22:40
question
Mathematics, 14.04.2021 22:40
question
Mathematics, 14.04.2021 22:40
question
Mathematics, 14.04.2021 22:40
question
Mathematics, 14.04.2021 22:40
question
Mathematics, 14.04.2021 22:40
question
Mathematics, 14.04.2021 22:40
Questions on the website: 13722367