Your project to obtain charitable donations is now 42 days into a planned 52-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 37 days of the project and to bring in $25,800. Even though we are 42 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to run for 42 days starting on day 5 and extending through day 47. We estimate that, even though we should have (37/42) 88.10% of this activity complete, it is actually only 55% complete. This part of the project was scheduled to bring in $150,800 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $51,600. So far $179,000 has actually been brought in on the project a. Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index.
b. Find the following:a) Schedule Variance ($) =b) Scheudle Performance Index =c) Cost Variance ($) =d) Coster Performance Index =

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:00
On april 1, 2017, jiro nozomi created a new travel agency, adventure travel. the following transactions occurred during the company’s first month. april 1 nozomi invested $30,000 cash and computer equipment worth $20,000 in the company in exchange for common stock.2 the company rented furnished office space by paying $1,800 cash for the first month's (april) rent.3 the company purchased $1,000 of office supplies for cash.10 the company paid $2,400 cash for the premium on a 12-month insurance policy. coverage begins on april 11.14 the company paid $1,600 cash for two weeks' salaries earned by employees.24 the company collected $8,000 cash on commissions from airlines on tickets obtained for customers.28 the company paid $1,600 cash for two weeks' salaries earned by employees.29 the company paid $350 cash for minor repairs to the company's computer.30 the company paid $750 cash for this month's telephone bill.30 the company paid $1,500 cash in dividends. the company's chart of accounts follows: 101 cash 405 commissions earned106 accounts receivable 612 depreciation expense—computer equip.124 office supplies 622 salaries expense128 prepaid insurance 637 insurance expense167 computer equipment 640 rent expense168 accumulated depreciation—computer equip. 650 office supplies expense209 salaries payable 684 repairs expense307 common stock 688 telephone expense318 retained earnings 901 income summary319 dividends use the following information: two-thirds (or $133) of one month’s insurance coverage has expired.at the end of the month, $600 of office supplies are still available.this month’s depreciation on the computer equipment is $500.employees earned $420 of unpaid and unrecorded salaries as of month-end.the company earned $1,750 of commissions that are not yet billed at month-end. required: 1. & 2. prepare journal entries to record the transactions for april and post them to the ledger accounts in requirement 6b. the company records prepaid and unearned items in balance sheet accounts.3. using account balances from requirement 6b, prepare an unadjusted trial balance as of april 30.4. journalize and post the adjusting entries for the month and prepare the adjusted trial balance.5a. prepare the income statement for the month of april 30, 2017.5b. prepare the statement of retained earnings for the month of april 30, 2017.5c. prepare the balance sheet at april 30, 2017.6a. prepare journal entries to close the temporary accounts and then post to requirement 6b.6b. post the journal entries to the ledger.7. prepare a post-closing trial balance.
Answers: 3
question
Business, 22.06.2019 19:00
Gus needs to purée his soup while it's still in the pot. what is the best tool for him to use? a. potato masher b. immersion blender c. rotary mixer d. whisk
Answers: 2
question
Business, 22.06.2019 20:20
Direct materials (4.2 x $15) $ 63direct labor ($12 x 17.5) $210manufacturing overhead ($2.40 x 17.5) $42total job cost $ 315dougan, inc. allocates overhead based on a predetermined overhead rate of $2.40 per direct labor hour. employees are paid $12.00 per hour. job 24 requires 4.2 pounds of direct materials at a cost of $15.00 per pound. employees worked a total of 17.5 hours to complete the job. actual manufacturing overhead costs totaled $80,000 for the year for the company. how much is the cost of job 24?
Answers: 1
question
Business, 22.06.2019 22:30
Perry is a freshman, he estimates that the cost of tuition, books, room and board, transportation, and other incidentals will be $30000 this year. he expects these costs to rise about $1500 each year while he is in college. if it will take him 5 years to earn his bs, what is the present cost of his degree at an interest rate of 6%? if he earns and extra $10000 annually for 40 years, what is the present worth of his degree.?
Answers: 3
You know the right answer?
Your project to obtain charitable donations is now 42 days into a planned 52-day project. The projec...
Questions
question
History, 17.10.2021 05:20
question
English, 17.10.2021 05:20
question
Mathematics, 17.10.2021 05:20
question
Biology, 17.10.2021 05:20
question
History, 17.10.2021 05:20
question
Biology, 17.10.2021 05:20
question
Biology, 17.10.2021 05:20
question
English, 17.10.2021 05:30
question
Chemistry, 17.10.2021 05:30
question
Law, 17.10.2021 05:30
Questions on the website: 13722359