Business, 09.12.2022 09:20 ninilizovtskt

You are working on a project with a pv of $56,733 and an spi of 1,2. what's the earned value of your project?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 19:50
On july 7, you purchased 500 shares of wagoneer, inc. stock for $21 a share. on august 1, you sold 200 shares of this stock for $28 a share. you sold an additional 100 shares on august 17 at a price of $25 a share. the company declared a $0.95 per share dividend on august 4 to holders of record as of wednesday, august 15. this dividend is payable on september 1. how much dividend income will you receive on september 1 as a result of your ownership of wagoneer stock
Answers: 1
question
Business, 23.06.2019 01:30
Lee earns $1,482 of interest in 270 days after making a deposit of $15,200. find the interest rate.
Answers: 1
question
Business, 23.06.2019 08:30
The hypothetical country of eurica is experiencing severe competition to its domestic auto industry in the form of foreign imports. many jobs are threatened. eurica places a 25 percent tariff on the price of imported cars. this type of tariff is known as a(n) tariff.
Answers: 1
question
Business, 23.06.2019 11:00
The average month end closing stock price for company a over the past year is $34.57 with a standard deviation of $4.65. the average month end closing stock price for company b over the same period is $26.15 with a standard deviation of $7.45. based on this data, we can conclude that the stock price for company a is more consistent when compared to the stock price for company b.
Answers: 3
You know the right answer?
You are working on a project with a pv of $56,733 and an spi of 1,2. what's the earned value of your...
Questions
question
Mathematics, 12.05.2021 03:00
question
Mathematics, 12.05.2021 03:00
question
Chemistry, 12.05.2021 03:00
question
Mathematics, 12.05.2021 03:00
question
Mathematics, 12.05.2021 03:00
question
Mathematics, 12.05.2021 03:00
Questions on the website: 13722362