The material requirements plan (mrp) uses which of the following to calculate requirements?
= bill of material, payroll schedule, and capacity plan
=master production schedule and capacity plan
= inventory data, production strategy, and supplier list
= master production schedule, bill of material, and inventory data

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 15:10
David is in week 3 of his current ashford course and has a paper due by monday night at midnight. he has finished everything but the concluding paragraph. as he boots up his computer to work on it, he sees a flash across the screen and then the screen goes black. he begins to panic as he tries desperately to turn the laptop back on. david should have saved his work on what kind of portable device?
Answers: 2
question
Computers and Technology, 23.06.2019 17:00
Companies that implement and apply an information system effectively can create
Answers: 1
question
Computers and Technology, 23.06.2019 23:30
Worth 50 points answer them bc i am not sure if i am wrong
Answers: 1
question
Computers and Technology, 24.06.2019 22:00
What is a number system, and what is the total number of digits used in this system called? a number system is a system that uses different (options: a) numbers b) symbols c) codes d) digits e) alphabets) to represent different numbers. the total number of digits used in a number system is known as its (options: 1) processor 2) converter 3) radix 4) least significant digit 5) most significant digit)
Answers: 1
You know the right answer?
The material requirements plan (mrp) uses which of the following to calculate requirements?
=...
Questions
question
Mathematics, 24.10.2019 10:43
Questions on the website: 13722361