Achart that shows the resource (project team member) along with their allocated hours for each week is known as a(n):

select one:

a. project staffing chart

b. gantt chart

c. histogram

d. entity diagram

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 10:00
Businesses allocate resources for their best and most productive uses. the more a resource, the more costly it will be. a manufacturer that requires scarce and costly resources is likely to charge for its products.
Answers: 2
question
Computers and Technology, 22.06.2019 17:30
Under which key category do the page up and page down keys fall? page up and page down keys fall under the keys category.
Answers: 1
question
Computers and Technology, 23.06.2019 05:20
What did creator markus “notch" persson initially call his game
Answers: 1
question
Computers and Technology, 23.06.2019 07:00
What are three software programs for mobile computing?
Answers: 1
You know the right answer?
Achart that shows the resource (project team member) along with their allocated hours for each week...
Questions
question
Arts, 10.11.2020 21:40
question
Health, 10.11.2020 21:40
question
Mathematics, 10.11.2020 21:40
Questions on the website: 13722362