We are given as input a set of n jobs, where job j has a processing time pj, a deadline dj. Given a schedule (i. e., an ordering of the jobs), consider that each job j has the completion time C; we define the lateness l of job j as the amount of time C - d, after its deadline that the job completes, or as 0 if C; < dj. Our goal is to minimize the maximum lateness, maxlj. Consider the following greedy rules for producing an ordering that minimizes the maximum lateness. For each rule, please explain why it gives the optimal ordering or give a counterexample. You can assume that all processing times and dead- lines are distinct.
(a) Schedule the requests in increasing order of processing time Pj.
(b) Schedule the requests in increasing order of the product d; * Pj.
(c) Schedule the requests in increasing order of deadline di.

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 07:30
Jasper and samantha are in a robotics competition. the guidelines state that the robots should be able to move a 10-gram weight at least 2 meters and turn in a circle. jasper and samantha have already built the robot. which step of the design process should they follow next to decide whether their robot meets the minimum criteria for the competition?
Answers: 1
question
Computers and Technology, 23.06.2019 14:30
Select the correct answer. what does it indicate when a website displays https instead of http? a. the website is secure. b. there is no secure sockets layer. c. the secure sockets layer is hidden. d. the website is not secure.
Answers: 1
question
Computers and Technology, 24.06.2019 01:30
How can you make your column headings stand out?
Answers: 1
question
Computers and Technology, 24.06.2019 06:30
Adrawing that places all lines parallel to the z axis at an angle from the horizon is 99 ! a. an oblique drawing b. a perspective drawing c. an auxiliary view d. a one-point perspective drawing
Answers: 2
You know the right answer?
We are given as input a set of n jobs, where job j has a processing time pj, a deadline dj. Given a...
Questions
question
Chemistry, 04.02.2020 04:49
Questions on the website: 13722362